1000 N AMALFI DR 90272
Certificate Information: 1000 N AMALFI DR 90272
- Application / Permit
- 24014-30000-00978
- Plan Check / Job No.
- B24WL00541
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION OF 2ND STORY AND ATTACHED TRELLIS TO (E) SFD AND ADDITION TO ATTACHED GARAGE
- Permit Issued
- Issued on 7/10/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 7/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2024 | YASHAR EMAMI |
| Corrections Issued | 4/2/2024 | YASHAR EMAMI |
| Quality Review Completed | 4/8/2024 | REZA HAGHIGHAT |
| Building Plans Picked Up | 4/8/2024 | APPLICANT |
| Plan Check Approved | 7/8/2024 | YASHAR EMAMI |
| Issued | 7/10/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2024 | DARIN LAM |
| Hydrant and Access approval | Cleared | 5/17/2024 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 6/26/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/27/2024 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 7/8/2024 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 7/8/2024 | YASHAR EMAMI |
Contact Information
| Architect | Blumenberg,, Richard Leo; Lic. No.: C10862 | 15200 SUNSET BLVD STE 201 PACIFIC PALISADES, CA 90272 |
| Contractor | Saridakis Kostandinos; Lic. No.: 1007393-B | 2800 28TH ST STE 133 SANTA MONICA, CA 90405 |
| Engineer | Howe,, Carl William; Lic. No.: C44773 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2024 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 9/19/2024 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/20/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/20/2024 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/24/2024 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/24/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/10/2024 | Approved | EVAN COOPER |
| Special/Order Compliance | 10/11/2024 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Steel/Welding | 10/21/2024 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/14/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Deputy Wood Construction | 11/25/2024 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 3/6/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/11/2025 | Approved | KENNETH NAGLE |
| Gas Test | 3/18/2025 | Approved | TEMISTOCLES CAAL |
| Masonry Wall/Backfill | 3/19/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 3/26/2025 | Partial Approval | HERBERT GIRON |
| Shower Pan | 3/26/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 4/1/2025 | Not Ready for Inspection | HERBERT GIRON |
| Shower Pan | 4/1/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 4/3/2025 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 4/15/2025 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 4/25/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/2/2025 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/29/2025 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 6/3/2025 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 6/3/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 6/3/2025 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 6/3/2025 | Approved | MEL KHACHATOURIAN |
| Insulation | 6/10/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Insulation | 6/11/2025 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 6/24/2025 | Approved | HERBERT GIRON |
| Service/Power Release | 7/15/2025 | Not Ready for Inspection | HERBERT GIRON |
| Underground Mechanical | 7/15/2025 | Partial Approval | HERBERT GIRON |
| Service/Power Release | 7/30/2025 | Partial Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/18/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 8/18/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Final | 8/18/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 8/21/2025 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 8/27/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 9/4/2025 | Not Ready for Inspection | HERBERT GIRON |
| Special/Order Compliance | 9/4/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 9/15/2025 | Corrections Issued | HERBERT GIRON |
| Gas Test | 9/15/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 9/15/2025 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 9/15/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 9/16/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 9/19/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 9/19/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 9/19/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 9/22/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 9/22/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Final | 9/22/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 11/18/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 11/18/2025 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 11/18/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 11/18/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/19/2025 | Approved | HERBERT GIRON |
| Smoke Detectors | 11/19/2025 | Approved | HERBERT GIRON |