1000 N AMALFI DR 90272

Certificate Information: 1000 N AMALFI DR 90272

Application / Permit
24014-30000-00978
Plan Check / Job No.
B24WL00541
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION OF 2ND STORY AND ATTACHED TRELLIS TO (E) SFD AND ADDITION TO ATTACHED GARAGE
Permit Issued
Issued on 7/10/2024
Issuing Office
West Los Angeles
Current Status
Issued on 7/10/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/11/2024 APPLICANT
Assigned to Plan Check Engineer 3/13/2024 YASHAR EMAMI
Corrections Issued 4/2/2024 YASHAR EMAMI
Quality Review Completed 4/8/2024 REZA HAGHIGHAT
Building Plans Picked Up 4/8/2024 APPLICANT
Plan Check Approved 7/8/2024 YASHAR EMAMI
Issued 7/10/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/17/2024 DARIN LAM
Hydrant and Access approval Cleared 5/17/2024 JOHN CONNEALLY
Low Impact Development (LID) Cleared 6/26/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 6/27/2024 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 7/8/2024 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 7/8/2024 YASHAR EMAMI

Contact Information

Architect Blumenberg,, Richard Leo; Lic. No.: C10862 15200 SUNSET BLVD STE 201      PACIFIC PALISADES, CA 90272
Contractor Saridakis Kostandinos; Lic. No.: 1007393-B 2800 28TH ST STE 133      SANTA MONICA, CA 90405
Engineer Howe,, Carl William; Lic. No.: C44773 4358 SEPULVEDA BLVD      CULVER CITY, CA 90230

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/9/2024 Partial Inspection KEVIN SARGSYAN
Deputy Drilled-In Anchors 9/19/2024 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 9/20/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 9/20/2024 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 9/24/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 9/24/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 10/10/2024 Approved EVAN COOPER
Special/Order Compliance 10/11/2024 Corrections Issued KEVIN SARGSYAN
Deputy Steel/Welding 10/21/2024 Conditional Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/14/2024 Not Ready for Inspection ARAM AVEDISIAN
Deputy Wood Construction 11/25/2024 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/6/2025 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Partial Approval EVAN COOPER
PLUMBING-Rough 3/6/2025 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 3/11/2025 Approved KENNETH NAGLE
Gas Test 3/18/2025 Approved TEMISTOCLES CAAL
Masonry Wall/Backfill 3/19/2025 Corrections Issued HERBERT GIRON
HVAC-Rough 3/26/2025 Partial Approval HERBERT GIRON
Shower Pan 3/26/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 4/1/2025 Not Ready for Inspection HERBERT GIRON
Shower Pan 4/1/2025 Approved HERBERT GIRON
ELECTRICAL-Rough 4/3/2025 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Not Ready for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 4/15/2025 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 4/25/2025 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 5/2/2025 Approved HERBERT GIRON
BUILDING-Rough-Frame 5/29/2025 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 6/3/2025 Approved MEL KHACHATOURIAN
Green Building Rough 6/3/2025 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 6/3/2025 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 6/3/2025 Approved MEL KHACHATOURIAN
Insulation 6/10/2025 No Access for Inspection MEL KHACHATOURIAN
Insulation 6/11/2025 Approved STEPHANIE SWANSON
Drywall Nailing 6/24/2025 Approved HERBERT GIRON
Service/Power Release 7/15/2025 Not Ready for Inspection HERBERT GIRON
Underground Mechanical 7/15/2025 Partial Approval HERBERT GIRON
Service/Power Release 7/30/2025 Partial Inspection STEPHANIE SWANSON
ELECTRICAL-Final 8/18/2025 No Access for Inspection MEL KHACHATOURIAN
HVAC-Final 8/18/2025 No Access for Inspection MEL KHACHATOURIAN
PLUMBING-Final 8/18/2025 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 8/21/2025 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 8/27/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 9/4/2025 Not Ready for Inspection HERBERT GIRON
Special/Order Compliance 9/4/2025 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 9/15/2025 Corrections Issued HERBERT GIRON
Gas Test 9/15/2025 Approved HERBERT GIRON
HVAC-Final 9/15/2025 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 9/15/2025 Corrections Issued HERBERT GIRON
HVAC-Final 9/16/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 9/19/2025 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 9/19/2025 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 9/19/2025 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 9/22/2025 No Access for Inspection MEL KHACHATOURIAN
HVAC-Final 9/22/2025 No Access for Inspection MEL KHACHATOURIAN
PLUMBING-Final 9/22/2025 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 11/18/2025 Approved HERBERT GIRON
HVAC-Final 11/18/2025 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 11/18/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Approved HERBERT GIRON
Smoke Detectors 11/18/2025 Corrections Issued HERBERT GIRON
HVAC-Final 11/19/2025 Approved HERBERT GIRON
Smoke Detectors 11/19/2025 Approved HERBERT GIRON