1447 S GLENVILLE DR 90035
Certificate Information: 1447 S GLENVILLE DR 90035
- Application / Permit
- 24014-30000-00750
- Plan Check / Job No.
- B24WL00424
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) garage to Accessory Dwelling Unit w/ addition on 1st story & 2nd story addition per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/14/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2024 | RICHARD GARCIA |
| Corrections Issued | 3/1/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 3/6/2024 | APPLICANT |
| Applicant returned to address corrections | 2/27/2025 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 4/10/2025 | AMY GUEVARRA |
| Plan Check Approved | 4/14/2025 | AMY GUEVARRA |
| Issued | 4/14/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/28/2024 | VASIL MIHALEV |
| Address approval | Cleared | 3/9/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 3/11/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 3/14/2024 | LIAM ODONOVAN |
| Miscellaneous | Cleared | 4/3/2025 | DIANA RENTERIA |
Contact Information
| Contractor | Cohen Construction Co Inc; Lic. No.: 962357-B | 3115 S CANFIELD AVE 3 LOS ANGELES, CA 90034 |
| Engineer | Khazra,, Afshin; Lic. No.: C50250 | 22855 PAUL REVERE DR CALABASAS, CA 91302 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/10/2025 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 6/17/2025 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 6/24/2025 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 6/27/2025 | Partial Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 7/8/2025 | Conditional Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 7/10/2025 | Partial Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 7/17/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | Corrections Issued | ASHLEY THOMPSON |
| Pre-Inspection | 9/25/2025 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 10/8/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 10/8/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 11/7/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 11/7/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 11/13/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 11/13/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 11/26/2025 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 11/26/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/2/2025 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/2/2025 | Partial Approval | CARLOS MATAMOROS |
| Deputy Wood Construction | 12/4/2025 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Rough | 12/9/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Partial Approval | ASHLEY THOMPSON |
| Green Building Rough | 12/10/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Insulation | 12/12/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/17/2025 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 1/8/2026 | Not Ready for Inspection | DANIEL VERA |
| Pre-Inspection | 1/8/2026 | Partial Inspection | DANIEL VERA |
| Wood Frame | 1/23/2026 | Corrections Issued | ASHLEY THOMPSON |
| Pre-Inspection | 2/10/2026 | Partial Inspection | WILBER ROSALES |
| Underground Mechanical | 2/10/2026 | Partial Inspection | WILBER ROSALES |
| Deputy Wood Construction | 2/11/2026 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 2/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Rough | 2/17/2026 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 2/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Rough | 2/17/2026 | Approved | WILBER ROSALES |
| Wood Frame | 2/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2026 | Partial Approval | RYAN SALAZAR |
| Wood Frame | 2/23/2026 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/27/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/27/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 2/27/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Shower Pan | 2/27/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Wood Frame | 2/27/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 3/9/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 3/9/2026 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2026 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 3/9/2026 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 3/9/2026 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 3/18/2026 | Conditional Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2026 | Conditional Approval | ASHLEY THOMPSON |
| Green Building Rough | 3/18/2026 | Approved | ASHLEY THOMPSON |
| Insulation | 3/23/2026 | Corrections Issued | WILBER ROSALES |
| Drywall Nailing | 4/2/2026 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/6/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 6/24/2026 | Corrections Issued | WILBER ROSALES |
| BUILDING-Rough-Frame | 6/25/2026 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 6/25/2026 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 6/25/2026 | Approved | ASHLEY THOMPSON |
| Green Building Final | 6/25/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Final | 6/25/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 7/1/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 7/1/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 7/1/2026 | Approved | ASHLEY THOMPSON |