12912 W MCCUNE AVE 90066
Certificate Information: 12912 W MCCUNE AVE 90066
- Application / Permit
- 24014-30000-00492
- Plan Check / Job No.
- B24WL00281
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and major remodel to an existing SFD ---1 OF 2---
- Permit Issued
- Issued on 4/1/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | KAVIAN REFAHI |
| Corrections Issued | 2/10/2024 | KAVIAN REFAHI |
| Quality Review Completed | 2/13/2024 | REZA HAGHIGHAT |
| Building Plans Picked Up | 2/15/2024 | APPLICANT |
| Applicant returned to address corrections | 3/4/2024 | KAVIAN REFAHI |
| Plan Check Approved | 3/7/2024 | KAVIAN REFAHI |
| Issued | 4/1/2024 | APPLICANT |
| CofO in Progress | 6/26/2025 | MICHAEL ALLEN |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
| CofO Issued | 7/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/13/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2024 | DARIN LAM |
| Sewer availability | Cleared | 2/13/2024 | DARIN LAM |
| Specific Plan | Cleared | 2/21/2024 | ALESSANDRO MERCURI |
| Low Impact Development (LID) | Cleared | 2/23/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 2/23/2024 | ANDREA SAINT-ANTONIN |
| GPI Written Notices | Cleared | 3/4/2024 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 3/4/2024 | KAVIAN REFAHI |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/7/2024 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 5/7/2024 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 5/9/2024 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/9/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/30/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 5/30/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/8/2024 | Corrections Issued | HERBERT GIRON |
| Gas Test | 8/8/2024 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 8/8/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 8/8/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 8/16/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 8/16/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/16/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/9/2024 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 9/11/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 9/11/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/11/2024 | Partial Approval | JESUS PINEDA |
| Verify Sprinkler Sign Off | 9/11/2024 | Approved | JESUS PINEDA |
| Insulation | 10/16/2024 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 10/22/2024 | Partial Approval | MICHAEL ALLEN |
| Insulation | 10/22/2024 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 10/28/2024 | Approved | JESUS PINEDA |
| Shower Pan | 11/19/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/3/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 6/12/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 6/12/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 6/12/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Not Ready | MICHAEL ALLEN |
| Smoke Detectors | 6/12/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 6/12/2025 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Final | 6/18/2025 | Approved | MICHAEL ALLEN |
| Final | 6/18/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 6/18/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | MICHAEL ALLEN |
| Service/Power Release | 6/18/2025 | Approved | MICHAEL ALLEN |
| Final | 6/25/2025 | OK to Issue CofO | MICHAEL ALLEN |