12912 W MCCUNE AVE 90066

Certificate Information: 12912 W MCCUNE AVE 90066

Application / Permit
24014-30000-00492
Plan Check / Job No.
B24WL00281
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and major remodel to an existing SFD ---1 OF 2---
Permit Issued
Issued on 4/1/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 KAVIAN REFAHI
Corrections Issued 2/10/2024 KAVIAN REFAHI
Quality Review Completed 2/13/2024 REZA HAGHIGHAT
Building Plans Picked Up 2/15/2024 APPLICANT
Applicant returned to address corrections 3/4/2024 KAVIAN REFAHI
Plan Check Approved 3/7/2024 KAVIAN REFAHI
Issued 4/1/2024 APPLICANT
CofO in Progress 6/26/2025 MICHAEL ALLEN
Permit Finaled 7/7/2025 RICHARD STEINBACH
CofO Issued 7/7/2025 RICHARD STEINBACH
Permit Finaled 7/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/13/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 2/13/2024 DARIN LAM
Sewer availability Cleared 2/13/2024 DARIN LAM
Specific Plan Cleared 2/21/2024 ALESSANDRO MERCURI
Low Impact Development (LID) Cleared 2/23/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 2/23/2024 ANDREA SAINT-ANTONIN
GPI Written Notices Cleared 3/4/2024 KAVIAN REFAHI
Grading Pre-Inspection Cleared 3/4/2024 KAVIAN REFAHI

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/7/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 5/7/2024 Partial Approval JESUS RODRIGUEZ
Sewer 5/7/2024 Approved JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/9/2024 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 5/9/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/30/2024 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Conditional Approval JESUS RODRIGUEZ
Green Building Rough 5/30/2024 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 8/8/2024 Corrections Issued HERBERT GIRON
Gas Test 8/8/2024 Partial Approval HERBERT GIRON
HVAC-Rough 8/8/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 8/8/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 8/16/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 8/16/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 8/16/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 9/9/2024 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 9/11/2024 Approved JESUS PINEDA
Green Building Rough 9/11/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 9/11/2024 Partial Approval JESUS PINEDA
Verify Sprinkler Sign Off 9/11/2024 Approved JESUS PINEDA
Insulation 10/16/2024 Corrections Issued JESUS PINEDA
Drywall Nailing 10/22/2024 Partial Approval MICHAEL ALLEN
Insulation 10/22/2024 Approved MICHAEL ALLEN
Drywall Nailing 10/28/2024 Approved JESUS PINEDA
Shower Pan 11/19/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 12/3/2024 Approved JESUS PINEDA
ELECTRICAL-Final 6/12/2025 Corrections Issued MICHAEL ALLEN
HVAC-Final 6/12/2025 Approved MICHAEL ALLEN
PLUMBING-Final 6/12/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Not Ready MICHAEL ALLEN
Smoke Detectors 6/12/2025 Approved MICHAEL ALLEN
Special/Order Compliance 6/12/2025 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Final 6/18/2025 Approved MICHAEL ALLEN
Final 6/18/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 6/18/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/18/2025 SGSOV Approved MICHAEL ALLEN
Service/Power Release 6/18/2025 Approved MICHAEL ALLEN
Final 6/25/2025 OK to Issue CofO MICHAEL ALLEN