14121 W CALIFA ST 91401
Certificate Information: 14121 W CALIFA ST 91401
- Application / Permit
- 24014-30000-00461
- Plan Check / Job No.
- B23LA24043
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ***ePlan*** (E) Garage conversion into a (N) ADU with addition
- Permit Issued
- Issued on 11/11/2024
- Issuing Office
- Current Status
- CofO Issued on 12/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | YASHAR EMAMI |
| Corrections Issued | 2/1/2024 | YASHAR EMAMI |
| Quality Review Completed | 2/12/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 7/8/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 8/28/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 9/12/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 9/18/2024 | YASHAR EMAMI |
| Plan Check Approved | 9/24/2024 | YASHAR EMAMI |
| Plan Check Approved | 9/24/2024 | REZA HAGHIGHAT |
| Issued | 11/11/2024 | APPLICANT |
| CofO in Progress | 10/28/2025 | RYAN SALAZAR |
| CofO in Progress | 10/28/2025 | RYAN SALAZAR |
| Permit Finaled | 12/11/2025 | RUBEN SALAS |
| CofO Issued | 12/11/2025 | RUBEN SALAS |
| Permit Finaled | 12/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/23/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 5/24/2024 | CARLOS RAMIREZ |
| Low Impact Development (LID) | Cleared | 9/13/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/16/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Italuce Construction And Development; Lic. No.: 924129-B | , |
| Contractor | Italuce Corporation; Lic. No.: 924129-B | , |
| Engineer | Habibi,, Shayaan; Lic. No.: C94225 | 10535 WILSHIRE BLVD APT 1602 LOS ANGELES, CA 90024 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/15/2024 | No Access for Inspection | RYAN SALAZAR |
| Pre-Inspection | 11/19/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 12/4/2024 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 12/9/2024 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 12/17/2024 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/11/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 3/11/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Wood Frame | 3/20/2025 | Corrections Issued | MISAEL ESPARZA |
| Special/Order Compliance | 3/28/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/16/2025 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/16/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 4/16/2025 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 4/16/2025 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 4/16/2025 | Approved | RYAN SALAZAR |
| Wood Frame | 4/16/2025 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/13/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 5/14/2025 | Approved | RYAN SALAZAR |
| Insulation | 5/29/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/29/2025 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 6/25/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/8/2025 | Approved | MICHAEL CORTEZ |
| Sewer | 8/6/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 8/6/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 8/25/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/14/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 10/14/2025 | Approved | RYAN SALAZAR |
| Final | 10/14/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 10/14/2025 | Approved | RYAN SALAZAR |
| HVAC-Final | 10/14/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 10/14/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 10/14/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 10/14/2025 | Approved | RYAN SALAZAR |
| Final | 10/27/2025 | Partial Approval | RYAN SALAZAR |
| Service/Power Release | 10/27/2025 | Approved | RYAN SALAZAR |