Permit Issued
Issued on 11/11/2024
Issuing Office
Current Status
CofO Issued on 12/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 YASHAR EMAMI
Corrections Issued 2/1/2024 YASHAR EMAMI
Quality Review Completed 2/12/2024 REZA HAGHIGHAT
Applicant returned to address corrections 7/8/2024 YASHAR EMAMI
Applicant returned to address corrections 8/28/2024 YASHAR EMAMI
Applicant returned to address corrections 9/12/2024 YASHAR EMAMI
Applicant returned to address corrections 9/18/2024 YASHAR EMAMI
Plan Check Approved 9/24/2024 YASHAR EMAMI
Plan Check Approved 9/24/2024 REZA HAGHIGHAT
Issued 11/11/2024 APPLICANT
CofO in Progress 10/28/2025 RYAN SALAZAR
CofO in Progress 10/28/2025 RYAN SALAZAR
Permit Finaled 12/11/2025 RUBEN SALAS
CofO Issued 12/11/2025 RUBEN SALAS
Permit Finaled 12/11/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/23/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/24/2024 CARLOS RAMIREZ
Sewer availability Cleared 5/24/2024 CARLOS RAMIREZ
Low Impact Development (LID) Cleared 9/13/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/16/2024 CARLOS AGUILERA

Contact Information

Contractor Italuce Construction And Development; Lic. No.: 924129-B       ,
Contractor Italuce Corporation; Lic. No.: 924129-B       ,
Engineer Habibi,, Shayaan; Lic. No.: C94225 10535 WILSHIRE BLVD APT 1602      LOS ANGELES, CA 90024

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/15/2024 No Access for Inspection RYAN SALAZAR
Pre-Inspection 11/19/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 12/4/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 12/9/2024 Approved RYAN SALAZAR
Deputy Drilled-In Anchors 12/17/2024 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 3/11/2025 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval RYAN SALAZAR
Green Building Rough 3/11/2025 Not Ready for Inspection RYAN SALAZAR
Wood Frame 3/20/2025 Corrections Issued MISAEL ESPARZA
Special/Order Compliance 3/28/2025 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 4/16/2025 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 4/16/2025 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 4/16/2025 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 4/16/2025 Partial Approval RYAN SALAZAR
PLUMBING-Rough 4/16/2025 Approved RYAN SALAZAR
Wood Frame 4/16/2025 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 5/13/2025 Approved RYAN SALAZAR
Shower Pan 5/14/2025 Approved RYAN SALAZAR
Insulation 5/29/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/29/2025 Partial Approval RYAN SALAZAR
Green Building Rough 6/25/2025 Approved RYAN SALAZAR
Drywall Nailing 7/8/2025 Approved MICHAEL CORTEZ
Sewer 8/6/2025 Approved KEVIN BERBERYAN
Underground Mechanical 8/6/2025 Approved KEVIN BERBERYAN
Underground Mechanical 8/25/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/14/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 10/14/2025 Approved RYAN SALAZAR
Final 10/14/2025 Corrections Issued RYAN SALAZAR
Green Building Final 10/14/2025 Approved RYAN SALAZAR
HVAC-Final 10/14/2025 Approved RYAN SALAZAR
PLUMBING-Final 10/14/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved RYAN SALAZAR
Service/Power Release 10/14/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 10/14/2025 Approved RYAN SALAZAR
Final 10/27/2025 Partial Approval RYAN SALAZAR
Service/Power Release 10/27/2025 Approved RYAN SALAZAR