4036 N WESLIN AVE 91423
Certificate Information: 4036 N WESLIN AVE 91423
- Application / Permit
- 24014-30000-00445
- Plan Check / Job No.
- B24WL00258
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- convrt existing under floor area to habitable space. ** see comments **
- Permit Issued
- Issued on 1/31/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 1/31/2024 | KAVIAN REFAHI |
| Issued | 1/31/2024 | APPLICANT |
| CofO in Progress | 3/20/2025 | MISAEL ESPARZA |
| Permit Finaled | 4/17/2025 | RUBEN SALAS |
| CofO Issued | 4/17/2025 | RUBEN SALAS |
| Permit Finaled | 4/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/31/2024 | ALEXANDER HELFER |
Contact Information
| Architect | Belak-Berger,, Charles Peter; Lic. No.: C13657 | 521 W. ROSECRANS AVE. GARDENA, CA 902481514 |
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/22/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/22/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 1/22/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 1/22/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 1/22/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/29/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 1/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 1/29/2025 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/29/2025 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 1/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/4/2025 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/4/2025 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 2/4/2025 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 2/4/2025 | Conditional Approval | MISAEL ESPARZA |
| Insulation | 2/7/2025 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 2/7/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/10/2025 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 2/12/2025 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/17/2025 | Approved | MISAEL ESPARZA |
| Final | 3/17/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/17/2025 | Approved | MISAEL ESPARZA |
| Green Building Final | 3/17/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 3/17/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/17/2025 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 3/17/2025 | Approved | MISAEL ESPARZA |
| Final | 3/19/2025 | OK to Issue CofO | MISAEL ESPARZA |