1622 W DONALDSON ST 90026
Certificate Information: 1622 W DONALDSON ST 90026
- Application / Permit
- 24014-30000-00419
- Plan Check / Job No.
- B24WL00245
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel & 2nd story addition to (E) 1-story S.F.D.
- Permit Issued
- Issued on 5/31/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/31/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 2/5/2024 | HOOMAN HAJIZADEH |
| Quality Review Completed | 2/6/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 2/14/2024 | APPLICANT |
| Applicant returned to address corrections | 5/16/2024 | HOOMAN HAJIZADEH |
| Plan Check Approved | 5/30/2024 | HOOMAN HAJIZADEH |
| Issued | 5/31/2024 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 2/3/2024 | HOOMAN HAJIZADEH |
| Grading Pre-Inspection | Cleared | 2/3/2024 | HOOMAN HAJIZADEH |
| Hydrant and Access approval | Cleared | 4/5/2024 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 4/23/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 4/25/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 5/3/2024 | CHRISTINA BRACO |
| Tenant Habitability Plan | Cleared | 5/3/2024 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Cappola Elizabeth; Lic. No.: 1084095-B | 5715 N FIGUEROA ST 200 LOS ANGELES, CA 90042 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Jahanpour-Burke,, Hooshmand; Lic. No.: L8230 | 7848 W SAHARA AVE LAS VEGAS, NV 89117 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/7/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/23/2024 | Approved | LUIS CASTRO |
| Wood Frame | 12/11/2024 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 12/18/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 12/18/2024 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 1/24/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Sewer | 5/5/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 5/9/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 5/20/2025 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/27/2025 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/27/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 5/28/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Special/Order Compliance | 5/28/2025 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/11/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 7/11/2025 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 7/11/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/25/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 8/11/2025 | Approved | ALEX COLIN |
| Sewer | 8/14/2025 | Not Ready for Inspection | REGINA MENDEZ |
| Shower Pan | 9/9/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 10/7/2025 | Approved | ALEX COLIN |
| Sewer | 10/16/2025 | Approved | ALEX COLIN |
| Grounding or Bonding | 12/11/2025 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 2/9/2026 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 2/9/2026 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 2/9/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 4/27/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 4/27/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/27/2026 | Corrections Issued | HAMIK HARTOUNIAN |