3530 S BARRY AVE 90066

Certificate Information: 3530 S BARRY AVE 90066

Application / Permit
24014-30000-00387
Plan Check / Job No.
B24WL00234
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO AN EXISTING 1 STORY SFD WITH AN ATTACHED 2 CAR GARAGE.
Permit Issued
Issued on 4/5/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2024 APPLICANT
Assigned to Plan Check Engineer 2/1/2024 KAVIAN REFAHI
Corrections Issued 2/3/2024 KAVIAN REFAHI
Quality Review Completed 2/13/2024 REZA HAGHIGHAT
Building Plans Picked Up 2/16/2024 APPLICANT
Applicant returned to address corrections 3/4/2024 KAVIAN REFAHI
Plan Check Approved 4/3/2024 KAVIAN REFAHI
Issued 4/5/2024 APPLICANT
CofO in Progress 5/30/2025 WILBER ROSALES
Permit Finaled 6/5/2025 RICHARD STEINBACH
CofO Issued 6/5/2025 RICHARD STEINBACH
Permit Finaled 6/5/2025 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 3/12/2024 SAMUEL LINN
Eng Process Fee Ord 176,300 Cleared 3/15/2024 DARIN LAM
Roof/Waste drainage to street Cleared 3/15/2024 DARIN LAM
Sewer availability Cleared 3/15/2024 DARIN LAM
GPI Written Notices Cleared 4/3/2024 KAVIAN REFAHI
Grading Pre-Inspection Cleared 4/3/2024 KAVIAN REFAHI

Contact Information

Contractor Vip Construction 1 Inc; Lic. No.: 1097925-B 11038 BENWELL DRIVE APT D      LYNWOOD, CA 90262
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/2/2024 Partial Approval JESUS PINEDA
Sewer 5/2/2024 Approved JESUS PINEDA
HVAC-Rough 5/15/2024 Corrections Issued JESUS PINEDA
HVAC-Rough 5/16/2024 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 5/21/2024 Partial Approval JESUS PINEDA
Deputy Drilled-In Anchors 5/23/2024 Approved JESUS PINEDA
Excavation/Setback/Form/Re-Bar 5/23/2024 Approved JESUS PINEDA
Footing/Foundation/Slab 5/23/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 8/12/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/12/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 8/12/2024 Approved JESUS PINEDA
Deputy Wood Construction 9/4/2024 Conditional Approval MICHAEL PELHAM
Wood Frame 9/6/2024 Corrections Issued DANIEL VERA
BUILDING-Rough-Frame 10/11/2024 Approved DANIEL VERA
Green Building Rough 10/11/2024 Approved DANIEL VERA
HVAC-Rough 10/11/2024 Approved DANIEL VERA
Insulation 10/16/2024 Approved REGINA MENDEZ
Interior/Exterior Lathing 10/16/2024 Approved REGINA MENDEZ
Shower Pan 10/22/2024 Not Ready for Inspection REGINA MENDEZ
Shower Pan 10/23/2024 Approved MICHAEL ALLEN
Drywall Nailing 10/29/2024 Approved DANIEL VERA
Interior/Exterior Lathing 10/29/2024 Approved DANIEL VERA
Gas Test 2/27/2025 Approved DANIEL VERA
ELECTRICAL-Final 3/28/2025 Partial Approval WILBER ROSALES
HVAC-Final 3/28/2025 Partial Approval WILBER ROSALES
PLUMBING-Final 3/28/2025 Corrections Issued WILBER ROSALES
Deputy Wood Construction 5/1/2025 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Final 5/5/2025 Approved WILBER ROSALES
PLUMBING-Final 5/5/2025 Approved WILBER ROSALES
HVAC-Final 5/7/2025 Approved WILBER ROSALES
Service/Power Release 5/7/2025 Approved WILBER ROSALES
Final 5/23/2025 Corrections Issued WILBER ROSALES
Green Building Final 5/23/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/23/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 5/23/2025 Approved WILBER ROSALES
Final 5/29/2025 OK to Issue CofO WILBER ROSALES