1926 S WESTHOLME AVE 90025
Certificate Information: 1926 S WESTHOLME AVE 90025
- Application / Permit
- 24014-30000-00218
- Plan Check / Job No.
- B24WL00145
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition to (e) 2-story SFD
- Permit Issued
- Issued on 4/2/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | REZA HAGHIGHAT |
| Corrections Issued | 2/9/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 2/20/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 2/22/2024 | APPLICANT |
| Applicant returned to address corrections | 9/10/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 11/4/2024 | REZA HAGHIGHAT |
| Issued | 4/2/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2024 | DARIN LAM |
| Sewer availability | Cleared | 2/20/2024 | DARIN LAM |
| GPI Written Notices | Cleared | 9/10/2024 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 9/10/2024 | REZA HAGHIGHAT |
| Low Impact Development (LID) | Cleared | 10/24/2024 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/26/2024 | DARIN LAM |
Contact Information
| Contractor | S O S Enterprises Inc; Lic. No.: 696896-B | 2355 WESTWOOD BLVD #201 LOS ANGELES, CA 90064 |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/24/2025 | Partial Approval | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 5/1/2025 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Corrections Issued | DANIEL VERA |
| Underground Mechanical | 5/12/2025 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | DANIEL VERA |
| Underground Mechanical | 5/14/2025 | Not Ready for Inspection | DANIEL VERA |
| Underground Mechanical | 5/16/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Partial Approval | DANIEL VERA |
| Sewer | 7/8/2025 | Approved | DANIEL VERA |
| Underground Mechanical | 7/8/2025 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2025 | Corrections Issued | DANIEL VERA |
| HVAC-Rough | 7/31/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 8/5/2025 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Rough | 8/7/2025 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 8/7/2025 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Partial Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 8/13/2025 | Corrections Issued | DANIEL VERA |
| Deputy Wood Construction | 8/14/2025 | Conditional Approval | DANIEL VERA |
| PLUMBING-Final | 8/14/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Rough | 8/14/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Partial Approval | DANIEL VERA |
| Wood Frame | 8/22/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 9/3/2025 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 9/3/2025 | Approved | DANIEL VERA |
| Shower Pan | 9/3/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 9/15/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 9/15/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Rough | 9/15/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 9/17/2025 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 9/18/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 9/18/2025 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 9/19/2025 | Conditional Approval | DANIEL VERA |
| Green Building Rough | 9/19/2025 | Approved | DANIEL VERA |
| HVAC-Final | 9/19/2025 | Corrections Issued | DANIEL VERA |
| HVAC-Rough | 9/19/2025 | Approved | DANIEL VERA |
| Insulation | 9/25/2025 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 10/1/2025 | Not Ready for Inspection | DANIEL VERA |
| Insulation | 10/1/2025 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 10/3/2025 | Approved | DANIEL VERA |
| Insulation | 10/3/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 10/15/2025 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/15/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/20/2025 | Approved | DANIEL VERA |
| Gas Test | 3/27/2026 | Corrections Issued | CHRISTOPHER WILSON |
| Gas Test | 4/6/2026 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 5/28/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 5/28/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Final | 6/10/2026 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 6/10/2026 | Corrections Issued | CARLOS MATAMOROS |