7401-7401 1/2 N GAYNOR AVE 91406

Certificate Information: 7401-7401 1/2 N GAYNOR AVE 91406

Application / Permit
24014-20002-03842
Plan Check / Job No.
B25VN05953
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 24014-20000-03842 TO REVISE THE SCOPE TO (N) 24'10" X 25'11" ATTACHED JUNIOR ACESSORY DWELLING UNIT AS PER GC 66323(a)(1) ADDITION TO (E) SFD , ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/21/2025
Issuing Office
Current Status
Permit Finaled on 9/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2025 APPLICANT
Assigned to Plan Check Engineer 3/5/2025 RARES BODEA
Corrections Issued 3/5/2025 RARES BODEA
Plan Check Approved 3/21/2025 RARES BODEA
Issued 3/21/2025 APPLICANT
Permit Finaled 9/16/2025 GAREN HAYRAPETYAN

Permit Application Clearance Information

Address approval Cleared 3/9/2025 RYAN CASTRO
Sewer availability Cleared 3/9/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/18/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/4/2025 Approved SALVADOR MARTINEZ
Insulation 4/18/2025 Corrections Issued JOAQUIN GREENOUGH
Pre-Inspection 4/18/2025 Corrections Issued JOAQUIN GREENOUGH
Insulation 4/22/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 4/22/2025 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/5/2025 Partial Approval WILLIAM WREN
Insulation 5/5/2025 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval SALVADOR MARTINEZ
ELECTRICAL-Rough 5/21/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 5/21/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/22/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 5/22/2025 Approved SALVADOR MARTINEZ
Green Building Rough 5/22/2025 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 5/22/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 5/22/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/30/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 5/30/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 5/30/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/6/2025 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 6/6/2025 Approved JOAQUIN GREENOUGH
Insulation 6/11/2025 Approved MICHAEL CORTEZ
Shower Pan 6/11/2025 Approved MICHAEL CORTEZ
Drywall Nailing 6/16/2025 Partial Approval SALVADOR MARTINEZ
Interior/Exterior Lathing 6/16/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 6/20/2025 Approved JACK KARGODORIAN