7401-7401 1/2 N GAYNOR AVE 91406
Certificate Information: 7401-7401 1/2 N GAYNOR AVE 91406
- Application / Permit
- 24014-20002-03842
- Plan Check / Job No.
- B25VN05953
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO 24014-20000-03842 TO REVISE THE SCOPE TO (N) 24'10" X 25'11" ATTACHED JUNIOR ACESSORY DWELLING UNIT AS PER GC 66323(a)(1) ADDITION TO (E) SFD , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- Current Status
- Permit Finaled on 9/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2025 | RARES BODEA |
| Corrections Issued | 3/5/2025 | RARES BODEA |
| Plan Check Approved | 3/21/2025 | RARES BODEA |
| Issued | 3/21/2025 | APPLICANT |
| Permit Finaled | 9/16/2025 | GAREN HAYRAPETYAN |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 3/9/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Approved | SALVADOR MARTINEZ |
| Insulation | 4/18/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Pre-Inspection | 4/18/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 4/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 4/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/5/2025 | Partial Approval | WILLIAM WREN |
| Insulation | 5/5/2025 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Partial Approval | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/22/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 5/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 5/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/22/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 5/30/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 5/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/6/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 6/6/2025 | Approved | JOAQUIN GREENOUGH |
| Insulation | 6/11/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 6/11/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 6/16/2025 | Partial Approval | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/16/2025 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 6/20/2025 | Approved | JACK KARGODORIAN |