1111 1/2 W 48TH ST 90037
Certificate Information: 1111 1/2 W 48TH ST 90037
- Application / Permit
- 24014-20002-00686
- Plan Check / Job No.
- B24VN20669
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: SUPPLEMENTAL TO 24014-2000-000686 TO UPDATE TO NEW CONSTRUCITON ADU, REVISE FRAMING/FOUNDATION PLAN, CHANGE E.O.R AND CONTRACTOR, UPDATE TITLE 24, AND UPDATE BUILDING SETBACKS ON SITEPLAN. ALL WORK PER ENG.
- Permit Issued
- Issued on 11/18/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2024 | JESSE ARELLANO |
| Corrections Issued | 10/30/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 11/4/2024 | APPLICANT |
| Applicant returned to address corrections | 11/14/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 11/18/2024 | LUISANGEL VALENZUELA |
| Issued | 11/18/2024 | APPLICANT |
| Permit Finaled | 4/11/2025 | BARRY HACHE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 11/15/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 11/15/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Ay Plumbing Construction Inc; Lic. No.: 1070029-B | PO BOX 33167 GRANADA HILLS, CA 91394 |
| Engineer | Mah,, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/3/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 12/3/2024 | Corrections Issued | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 12/9/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Underground Mechanical | 12/9/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 12/12/2024 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2024 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 12/30/2024 | Not Ready for Inspection | BARRY HACHE |
| Verify Sprinkler Sign Off | 12/30/2024 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 1/13/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 1/13/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 1/16/2025 | Corrections Issued | BARRY HACHE |
| Insulation | 1/16/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 1/16/2025 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 1/21/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Rough | 1/21/2025 | Approved | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 1/21/2025 | Corrections Issued | BARRY HACHE |
| Verify Sprinkler Sign Off | 1/21/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 1/22/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 1/22/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 1/22/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 1/23/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 1/24/2025 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 1/27/2025 | Approved | BARRY HACHE |
| Insulation | 1/27/2025 | Approved | BARRY HACHE |
| Insulation | 1/27/2025 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 1/27/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 1/27/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 1/30/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 1/30/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 3/26/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 3/26/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 3/26/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 3/26/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 4/1/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 4/1/2025 | Not Ready for Inspection | BARRY HACHE |
| Footing/Foundation/Slab | 4/1/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 4/1/2025 | Not Ready for Inspection | BARRY HACHE |
| Service/Power Release | 4/1/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 4/8/2025 | Not Ready for Inspection | BARRY HACHE |
| Footing/Foundation/Slab | 4/8/2025 | Approved | BARRY HACHE |
| Green Building Final | 4/8/2025 | Approved | BARRY HACHE |
| Final | 4/11/2025 | Permit Finaled | BARRY HACHE |
| Service/Power Release | 4/11/2025 | Approved | BARRY HACHE |