4844 N BILOXI AVE 91601
Certificate Information: 4844 N BILOXI AVE 91601
- Application / Permit
- 24014-20001-04362
- Plan Check / Job No.
- B25VN05758
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO 24014-20000-04362 TO REVISE THE SCOPE TO ADD 4'3" X 11'3" 1ST FLOOR AND 31'5 " X 17' 2ND FLOOR TO AND CONVERSION OF (E) 20'3" X 20'3" TWO CAR GARAGE AND (E) 11'3" X 16' STORAGE AND DRESSING ROOM TO ACCESSORY DWELLING UNIT AS PER LAMC 12.22 A.33(b)(1), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/1/2025
- Issuing Office
- Current Status
- Permit Finaled on 8/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | RARES BODEA |
| Corrections Issued | 3/10/2025 | RARES BODEA |
| Quality Review Completed | 3/12/2025 | STEVEN KIM |
| Plan Check Approved | 5/28/2025 | RARES BODEA |
| Issued | 6/1/2025 | APPLICANT |
| Permit Finaled | 8/18/2025 | ROBERTO PALACIOS-LOPEZ |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/15/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/15/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/15/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2025 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 5/13/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 5/13/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 28025 DOROTHY DR STE 202 AGOURA HILLS, CA 91301 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/4/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 7/18/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 7/24/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/24/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 7/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/11/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 8/11/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |