16539 W SUPERIOR ST 91343
Certificate Information: 16539 W SUPERIOR ST 91343
- Application / Permit
- 24014-20001-03667
- Plan Check / Job No.
- B24VN25533
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: SUPPLEMENTAL TO 24014-20000-03667 TO INCREASE ADDITION SIZE
- Permit Issued
- Issued on 12/27/2024
- Issuing Office
- Current Status
- Issued on 12/27/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2024 | DANIEL SANJUAN |
| Plan Check Approved | 12/19/2024 | DANIEL SANJUAN |
| No Progress | 12/26/2024 | DANIEL SANJUAN |
| Plan Check Approved | 12/26/2024 | DANIEL SANJUAN |
| No Progress | 12/26/2024 | DANIEL SANJUAN |
| Plan Check Approved | 12/26/2024 | DANIEL SANJUAN |
| No Progress | 12/26/2024 | DANIEL SANJUAN |
| Plan Check Approved | 12/26/2024 | DANIEL SANJUAN |
| Issued | 12/27/2024 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/7/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/23/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 1/23/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 1/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Special/Order Compliance | 1/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 2/3/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Insulation | 2/6/2025 | Partial Approval | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 3/10/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 3/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Partial Approval | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 3/10/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 3/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Insulation | 3/17/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Drywall Nailing | 3/20/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 3/24/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | Not Ready for Inspection | RAUL OLAGI |
| Special/Order Compliance | 4/18/2025 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Rough-Elec/Plmb/HVAC | 5/2/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 7/2/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/2/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 7/29/2025 | Partial Approval | LOUIS ESCOTO |
| Shower Pan | 7/29/2025 | Approved | LOUIS ESCOTO |
| Insulation | 8/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 8/5/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 8/12/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 8/12/2025 | Approved | SALVADOR MARTINEZ |