14075 W CHAMBERLAIN ST 91340

Certificate Information: 14075 W CHAMBERLAIN ST 91340

Application / Permit
24014-20001-03662
Plan Check / Job No.
B24VN24351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 24014-20000-03662 TO REVISE FLOOR PLAN AND EXTEND ADDITION
Permit Issued
Issued on 12/18/2024
Issuing Office
Current Status
Issued on 12/18/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/27/2024 APPLICANT
Assigned to Plan Check Engineer 12/6/2024 JEROME MAGAT PALMA
Corrections Issued 12/10/2024 JEROME MAGAT PALMA
Building Plans Picked Up 12/11/2024 APPLICANT
Plan Check Approved 12/18/2024 SERGIO MUNIZ
Issued 12/18/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/12/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/12/2024 EDGAR ALCARAZ

Contact Information

Contractor Munoz Carlos Enrique; Lic. No.: 908224-B 2027 PHILLIPPI STREET      SAN FERNANDO, CA 91340
Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/20/2024 Approved DAVID ANDERSON
PLUMBING-Rough 12/20/2024 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
Special/Order Compliance 12/26/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 12/27/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 12/27/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 12/27/2024 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/31/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/31/2024 Approved JENNIFER RABUCHIN
Green Building Rough 12/31/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 12/31/2024 Partial Approval JENNIFER RABUCHIN
METHANE-Rough 12/31/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 12/31/2024 Approved JENNIFER RABUCHIN
Insulation 1/6/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 1/6/2025 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 2/25/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/25/2025 Partial Approval JENNIFER RABUCHIN