5113 E TEMPLETON ST 90032

Certificate Information: 5113 E TEMPLETON ST 90032

Application / Permit
24014-20001-01120
Plan Check / Job No.
B24VN09327
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO 24014-20000-01120. REVISE SCOPE OF WORK TO "NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)."
Permit Issued
Issued on 8/27/2024
Issuing Office
Valley
Current Status
Permit Finaled on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/10/2024 JESSE ARELLANO
Corrections Issued 7/11/2024 JESSE ARELLANO
Building Plans Picked Up 7/15/2024 APPLICANT
Plan Check Approved 8/27/2024 ALEC MOUSAKHANIAN
Issued 8/27/2024 APPLICANT
Permit Finaled 5/5/2025 LILIANA PORTILLO

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/15/2024 MICHAEL TEMPLE
"D" conditions Cleared 7/16/2024 DAVID URITA
"Q" conditions Cleared 7/16/2024 DAVID URITA
BHO/Hillside ordinance Cleared 7/17/2024 CHRISTINA BRACO
BHO/Hillside ordinance Cleared 7/17/2024 CHRISTINA BRACO
BHO/Hillside ordinance Cleared 7/17/2024 CHRISTINA BRACO
BHO/Hillside ordinance Cleared 7/17/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 7/19/2024 CHRISTINA BRACO
Sewer availability Cleared 7/19/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 8/19/2024 AMBER CAMPBELL
GPI Written Notices Cleared 8/27/2024 ALEC MOUSAKHANIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/30/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 8/30/2024 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 10/15/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Partial Approval LILIANA PORTILLO
Rough-Elec/Plmb/HVAC 10/15/2024 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 10/15/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/25/2024 Corrections Issued LILIANA PORTILLO
Green Building Rough 10/25/2024 Approved LILIANA PORTILLO
Insulation 10/25/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 10/25/2024 Partial Approval LILIANA PORTILLO
Drywall Nailing 11/8/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 Approved LILIANA PORTILLO
Insulation 11/8/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 11/8/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 4/11/2025 Approved LILIANA PORTILLO
Final 4/11/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 4/11/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 4/11/2025 Not Ready for Inspection LILIANA PORTILLO
Final 4/21/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 4/21/2025 Approved LILIANA PORTILLO
HVAC-Final 4/21/2025 Approved LILIANA PORTILLO
PLUMBING-Final 4/21/2025 Approved LILIANA PORTILLO
Service/Power Release 4/21/2025 Not Ready for Inspection LILIANA PORTILLO
Final 5/5/2025 Permit Finaled LILIANA PORTILLO
Service/Power Release 5/5/2025 Approved LILIANA PORTILLO