12325-12327 W ADDISON ST 91607
Certificate Information: 12325-12327 W ADDISON ST 91607
- Application / Permit
- 24014-20000-05731
- Plan Check / Job No.
- B24VN27069
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- ePlan: Conversion of existing 2-car attached garage into a Junior Accessory Dwelling Unit per GCS 65852.2(e)(1)(A) AND 65852.22
- Permit Issued
- Issued on 2/21/2025
- Issuing Office
- Current Status
- CofO Issued on 6/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2025 | JOSEPH RAFOLS |
| Corrections Issued | 1/14/2025 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 1/22/2025 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 2/12/2025 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 2/14/2025 | LAWRENCE QUIRANTE |
| Plan Check Approved | 2/19/2025 | LAWRENCE QUIRANTE |
| Issued | 2/21/2025 | APPLICANT |
| CofO in Progress | 6/12/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 6/13/2025 | RUBEN SALAS |
| CofO Issued | 6/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 1/7/2025 | RYAN CASTRO |
| Specific Plan | Cleared | 1/13/2025 | JOANNA MARROQUIN |
Contact Information
| Architect | Sharif,, Mohamed; Lic. No.: NA39619 | , |
| Contractor | El Reef Construction Inc; Lic. No.: 978074-B | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/27/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 2/27/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 2/28/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 3/11/2025 | Approved | GAREN HAYRAPETYAN |
| Sewer | 3/11/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/18/2025 | Partial Approval | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 3/24/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 3/24/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 3/24/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 3/26/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Wood Frame | 3/26/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 3/27/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/28/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 3/28/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/1/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/2/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 4/2/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/7/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/7/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/6/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 6/6/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Final | 6/6/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Final | 6/6/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Final | 6/6/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 6/6/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 6/12/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |