13120 W BRANFORD ST 91331
Certificate Information: 13120 W BRANFORD ST 91331
- Application / Permit
- 24014-20000-05729
- Plan Check / Job No.
- B24VN27054
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) DETACHED GARAGE AND ADDITION TO (N) 37' x 18' 1" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2025 | ISIS ARGUETA |
| Corrections Issued | 1/13/2025 | ISIS ARGUETA |
| Plan Check Approved | 2/19/2025 | NAREG ATARIAN |
| Issued | 2/27/2025 | APPLICANT |
| CofO in Progress | 8/29/2025 | VINCENT HANLEY |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
| CofO Issued | 9/4/2025 | RUBEN SALAS |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/4/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 2/4/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/10/2025 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/8/2025 | Partial Approval | VINCENT HANLEY |
| Sewer | 4/8/2025 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 4/9/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/11/2025 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/18/2025 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/18/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/18/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/18/2025 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/7/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/7/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/7/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/7/2025 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 5/7/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/7/2025 | Approved | VINCENT HANLEY |
| Insulation | 5/15/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 5/15/2025 | Partial Approval | MICHAEL CORTEZ |
| Shower Pan | 5/15/2025 | Corrections Issued | MICHAEL CORTEZ |
| Drywall Nailing | 6/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 6/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Shower Pan | 6/12/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 7/2/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 7/2/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 7/18/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 8/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 8/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 8/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| MERV13>=Final | 8/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/21/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 8/28/2025 | Approved | VINCENT HANLEY |
| Final | 8/28/2025 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 8/28/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 8/28/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/28/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 8/28/2025 | Approved | VINCENT HANLEY |