CONVERT EXISTING GARAGE WITH ADDITIONS INTO 2-STORY(57'-10" X 23') IRREGULAR SHAPE) SINGLE FAMILY DWELLING PER SB9 TWO-UNIT DEVELOPMENT CA GOVT. CODE 65852.21 WITH AN ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 5/8/2025
Issuing Office
Current Status
CofO Issued on 4/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2024 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 VAHAN JIVALAGIAN
Corrections Issued 1/22/2025 VAHAN JIVALAGIAN
Quality Review Completed 1/27/2025 OMID HEDAYAT
Building Plans Picked Up 2/4/2025 APPLICANT
Plan Check Approved 4/17/2025 EDWARD MEHRABIAN
Issued 5/8/2025 APPLICANT
CofO in Progress 2/18/2026 MORRIS JACKSON
Permit Finaled 4/27/2026 JOHN JANSON
CofO Issued 4/27/2026 JOHN JANSON
Permit Finaled 4/27/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/5/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/5/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/11/2025 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/11/2025 JERRY KAO
Sewer availability Cleared 2/11/2025 CARLOS AGUILERA
Miscellaneous Cleared 3/14/2025 ANNA VIDAL
Senate Bill 9 Cleared 3/14/2025 GEORGIA SMITH
ZI Cleared 3/14/2025 GEORGIA SMITH
Construction near power lines Cleared 4/1/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 17770 CAPE JASMINE RD      CANYON COUNTRY, CA 91387

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/5/2025 Partial Approval MORRIS JACKSON
Footing/Foundation/Slab 6/9/2025 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 6/16/2025 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 6/23/2025 Not Ready for Inspection MORRIS JACKSON
Footing/Foundation/Slab 6/25/2025 Approved MORRIS JACKSON
Deputy Wood Construction 7/1/2025 Conditional Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 7/3/2025 Partial Approval MORRIS JACKSON
ELECTRICAL-Rough 7/28/2025 Approved MORRIS JACKSON
Gas Test 7/28/2025 Approved MORRIS JACKSON
PLUMBING-Rough 7/28/2025 Approved MORRIS JACKSON
Sewer 7/28/2025 Approved MORRIS JACKSON
Deputy Wood Construction 7/30/2025 Conditional Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 7/31/2025 Partial Approval MORRIS JACKSON
HVAC-Rough 7/31/2025 Approved MORRIS JACKSON
Shower Pan 7/31/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/12/2025 Corrections Issued MORRIS JACKSON
Interior/Exterior Lathing 8/12/2025 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 8/15/2025 Approved MORRIS JACKSON
Green Building Rough 8/15/2025 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 8/15/2025 Approved MORRIS JACKSON
Insulation 8/19/2025 Corrections Issued MORRIS JACKSON
Insulation 8/20/2025 Approved MORRIS JACKSON
Drywall Nailing 8/22/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 8/22/2025 Approved MORRIS JACKSON
Final 1/5/2026 Corrections Issued MORRIS JACKSON
Green Building Final 1/5/2026 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 1/5/2026 SGSOV Approved MORRIS JACKSON
Smoke Detectors 1/5/2026 Approved MORRIS JACKSON
ELECTRICAL-Rough 2/4/2026 Approved MORRIS JACKSON
Final 2/4/2026 Corrections Issued MORRIS JACKSON
PLUMBING-Rough 2/4/2026 Approved MORRIS JACKSON
Final 2/12/2026 OK to Issue CofO MORRIS JACKSON
Service/Power Release 2/12/2026 Approved MORRIS JACKSON