8543-8545 N NORRIS AVE 91352

Certificate Information: 8543-8545 N NORRIS AVE 91352

Application / Permit
24014-20000-05708
Plan Check / Job No.
B24VN26977
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 6'-2"X6'-0" PORTION OF (E) GARAGE TO LAUNDRY ROOM FOR (E) SFD AND CONVERT REMAINING PORTION WITH 16'-6" X 13'-4" ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e).
Permit Issued
Issued on 1/31/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2024 APPLICANT
Assigned to Plan Check Engineer 1/6/2025 ARTIN ZARUKIAN
Corrections Issued 1/6/2025 ARTIN ZARUKIAN
Building Plans Picked Up 1/16/2025 APPLICANT
Plan Check Approved 1/24/2025 KAMYAR EMAMI
Issued 1/31/2025 APPLICANT
CofO in Progress 3/12/2026 DAVID ANDERSON
Permit Finaled 4/21/2026 RUBEN SALAS
CofO Issued 4/21/2026 RUBEN SALAS
Permit Finaled 4/21/2026 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 1/8/2025 JASON CHAN
Miscellaneous Cleared 1/8/2025 JASON CHAN
Address approval Cleared 1/9/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/10/2025 RYAN CASTRO
Sewer availability Cleared 1/10/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 1/24/2025 CHRISTINE REUSCH

Contact Information

Contractor Owner-Builder       ,
Engineer Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 17770 CAPE JASMINE RD      CANYON COUNTRY, CA 91387

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/7/2025 Approved DAVID ANDERSON
PLUMBING-Rough 4/7/2025 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 4/11/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Partial Approval DAVID ANDERSON
Interior/Exterior Lathing 5/13/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 7/30/2025 Corrections Issued DAVID ANDERSON
HVAC-Rough 7/30/2025 Approved DAVID ANDERSON
PLUMBING-Rough 7/30/2025 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 8/15/2025 Approved DAVID ANDERSON
PLUMBING-Rough 8/15/2025 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 9/2/2025 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 9/2/2025 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 9/15/2025 Approved DAVID ANDERSON
PLUMBING-Rough 9/15/2025 Approved DAVID ANDERSON
Insulation 9/23/2025 Approved DAVID ANDERSON
Drywall Nailing 10/2/2025 Approved DAVID ANDERSON
Shower Pan 11/12/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 12/2/2025 Approved DAVID ANDERSON
ELECTRICAL-Final 2/26/2026 Corrections Issued DAVID ANDERSON
HVAC-Final 2/26/2026 Corrections Issued DAVID ANDERSON
PLUMBING-Final 2/26/2026 Approved DAVID ANDERSON
Final 3/11/2026 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/11/2026 SGSOV Approved DAVID ANDERSON
Smoke Detectors 3/11/2026 Approved DAVID ANDERSON