17222 W HORACE ST 91344

Certificate Information: 17222 W HORACE ST 91344

Application / Permit
24014-20000-05698
Plan Check / Job No.
B24VN26872
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AND ADDITION TO ACCESSORY DWELLING UNIT (ADU) PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 2/3/2025
Issuing Office
Current Status
CofO Issued on 8/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2024 APPLICANT
Assigned to Plan Check Engineer 12/31/2024 PINANK PATEL
Corrections Issued 1/1/2025 PINANK PATEL
Plan Check Approved 2/1/2025 PINANK PATEL
Issued 2/3/2025 APPLICANT
CofO in Progress 8/13/2025 STEVEN BACK
Permit Finaled 8/19/2025 JOHN JANSON
CofO Issued 8/19/2025 JOHN JANSON
Permit Finaled 8/19/2025 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 1/9/2025 RIDWAN HARDY
Address approval Cleared 1/13/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/14/2025 BIAINA HARITUNIAN
Sewer availability Cleared 1/14/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/16/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/25/2025 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 3/3/2025 Corrections Issued STEVEN BACK
PLUMBING-Rough 3/3/2025 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 3/5/2025 No Access for Inspection STEVEN BACK
Footing/Foundation/Slab 3/7/2025 Approved STEVEN BACK
PLUMBING-Rough 3/7/2025 Partial Approval STEVEN BACK
Sewer 3/7/2025 Approved STEVEN BACK
ELECTRICAL-Rough 4/23/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Partial Approval STEVEN BACK
HVAC-Rough 4/23/2025 Corrections Issued STEVEN BACK
PLUMBING-Rough 4/23/2025 Approved STEVEN BACK
Shower Pan 4/23/2025 Approved STEVEN BACK
Insulation 4/24/2025 No Access for Inspection STEVEN BACK
Interior/Exterior Lathing 4/28/2025 Partial Approval STEVEN BACK
Special/Order Compliance 4/28/2025 Corrections Issued STEVEN BACK
HVAC-Rough 5/5/2025 Approved JEFFREY PARD
BUILDING-Rough-Frame 5/7/2025 Partial Approval STEVEN BACK
Green Building Rough 5/7/2025 Approved STEVEN BACK
HVAC-Rough 5/7/2025 Approved STEVEN BACK
BUILDING-Rough-Frame 5/9/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Approved STEVEN BACK
Insulation 5/9/2025 Approved STEVEN BACK
Drywall Nailing 5/12/2025 Approved STEVEN BACK
Interior/Exterior Lathing 5/12/2025 Approved STEVEN BACK
Final 7/18/2025 Corrections Issued STEVEN BACK
Green Building Final 7/18/2025 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Approved STEVEN BACK
Smoke Detectors 7/18/2025 Corrections Issued STEVEN BACK
Final 7/25/2025 Corrections Issued STEVEN BACK
Green Building Final 7/25/2025 Approved STEVEN BACK
Smoke Detectors 7/25/2025 Approved STEVEN BACK
Final 8/13/2025 OK to Issue CofO STEVEN BACK
Service/Power Release 8/13/2025 Approved STEVEN BACK