17222 W HORACE ST 91344
Certificate Information: 17222 W HORACE ST 91344
- Application / Permit
- 24014-20000-05698
- Plan Check / Job No.
- B24VN26872
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND ADDITION TO ACCESSORY DWELLING UNIT (ADU) PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 2/3/2025
- Issuing Office
- Current Status
- CofO Issued on 8/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2024 | PINANK PATEL |
| Corrections Issued | 1/1/2025 | PINANK PATEL |
| Plan Check Approved | 2/1/2025 | PINANK PATEL |
| Issued | 2/3/2025 | APPLICANT |
| CofO in Progress | 8/13/2025 | STEVEN BACK |
| Permit Finaled | 8/19/2025 | JOHN JANSON |
| CofO Issued | 8/19/2025 | JOHN JANSON |
| Permit Finaled | 8/19/2025 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/9/2025 | RIDWAN HARDY |
| Address approval | Cleared | 1/13/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 1/14/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/16/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/25/2025 | Conditional Approval | STEVEN BACK |
| Footing/Foundation/Slab | 3/3/2025 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 3/3/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 3/5/2025 | No Access for Inspection | STEVEN BACK |
| Footing/Foundation/Slab | 3/7/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 3/7/2025 | Partial Approval | STEVEN BACK |
| Sewer | 3/7/2025 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 4/23/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 4/23/2025 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 4/23/2025 | Approved | STEVEN BACK |
| Shower Pan | 4/23/2025 | Approved | STEVEN BACK |
| Insulation | 4/24/2025 | No Access for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 4/28/2025 | Partial Approval | STEVEN BACK |
| Special/Order Compliance | 4/28/2025 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 5/5/2025 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/7/2025 | Partial Approval | STEVEN BACK |
| Green Building Rough | 5/7/2025 | Approved | STEVEN BACK |
| HVAC-Rough | 5/7/2025 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Approved | STEVEN BACK |
| Insulation | 5/9/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 5/12/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 5/12/2025 | Approved | STEVEN BACK |
| Final | 7/18/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 7/18/2025 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 7/18/2025 | Corrections Issued | STEVEN BACK |
| Final | 7/25/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 7/25/2025 | Approved | STEVEN BACK |
| Smoke Detectors | 7/25/2025 | Approved | STEVEN BACK |
| Final | 8/13/2025 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 8/13/2025 | Approved | STEVEN BACK |