5759 N LEMP AVE 91601

Certificate Information: 5759 N LEMP AVE 91601

Application / Permit
24014-20000-05670
Plan Check / Job No.
B24VN26698
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR SHAPED ADDITION TO (E) SFD.
Permit Issued
Issued on 1/8/2025
Issuing Office
Current Status
CofO Issued on 5/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2024 APPLICANT
Assigned to Plan Check Engineer 12/31/2024 ARTIN ZARUKIAN
Corrections Issued 1/4/2025 ARTIN ZARUKIAN
Building Plans Picked Up 1/6/2025 APPLICANT
Plan Check Approved 1/8/2025 SERGIO MUNIZ
Issued 1/8/2025 APPLICANT
CofO in Progress 5/13/2025 JAVIER RAMOS JR
CofO Issued 5/23/2025 RUBEN SALAS
Permit Finaled 5/23/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/6/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/6/2025 LEE GUILBEAUX
Sewer availability Cleared 1/6/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/6/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/27/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 1/29/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 2/3/2025 Approved CHRISTOPHER ROJAS
Gas Test 3/4/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/6/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 3/6/2025 Partial Inspection CHRISTOPHER ROJAS
Insulation 3/14/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/14/2025 Partial Approval CHRISTOPHER ROJAS
Shower Pan 3/14/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 3/20/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 3/20/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/20/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/2/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 5/2/2025 Approved JAVIER RAMOS JR
Final 5/2/2025 Partial Inspection JAVIER RAMOS JR
Green Building Final 5/2/2025 Approved JAVIER RAMOS JR
HVAC-Final 5/2/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 5/2/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 5/2/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/6/2025 Approved CHRISTOPHER ROJAS
Final 5/13/2025 OK to Issue CofO JAVIER RAMOS JR