20551 W VALERIO ST 91306
Certificate Information: 20551 W VALERIO ST 91306
- Application / Permit
- 24014-20000-05667
- Plan Check / Job No.
- B24VN26684
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & ADD 2-STORY **ePlan**
- Permit Issued
- Issued on 3/11/2025
- Issuing Office
- Current Status
- CofO in Progress on 4/15/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/28/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/2/2025 | JASON HEALEY |
| Applicant returned to address corrections | 2/19/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/3/2025 | NILOOFAR MEHRAIN |
| Issued | 3/11/2025 | APPLICANT |
| CofO in Progress | 4/15/2026 | ALEXANDER HANDY |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 1/15/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/21/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/25/2025 | Partial Approval | SCOTT SOBEL |
| Excavation/Setback/Form/Re-Bar | 4/23/2025 | Conditional Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 5/30/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 6/12/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Partial Approval | ALEXANDER HANDY |
| Shower Pan | 6/18/2025 | Corrections Issued | ALEXANDER HANDY |
| HVAC-Rough | 6/25/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 6/25/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 6/26/2025 | Not Ready for Inspection | SCOTT SOBEL |
| BUILDING-Rough-Frame | 6/30/2025 | Corrections Issued | TROY SANDERS |
| HVAC-Rough | 6/30/2025 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 7/7/2025 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/10/2025 | Conditional Approval | ALEXANDER HANDY |
| Green Building Rough | 7/10/2025 | Approved | ALEXANDER HANDY |
| Insulation | 7/10/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/10/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 7/16/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 10/7/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | ALEXANDER HANDY |
| Final | 10/22/2025 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 10/22/2025 | Approved | ALEXANDER HANDY |
| Green Building Final | 10/22/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV No Gas | ALEXANDER HANDY |
| Smoke Detectors | 10/22/2025 | Approved | ALEXANDER HANDY |
| Final | 12/18/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 12/18/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 3/3/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 3/3/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Special/Order Compliance | 3/3/2026 | Corrections Issued | ALEXANDER HANDY |
| Final | 4/3/2026 | No Access for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 4/3/2026 | No Access for Inspection | ARUTYUN MADATYAN |
| Final | 4/9/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 4/9/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 4/14/2026 | Approved | ALEXANDER HANDY |
| Final | 4/14/2026 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 4/14/2026 | Approved | ALEXANDER HANDY |
| HVAC-Final | 4/14/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 4/14/2026 | Approved | ALEXANDER HANDY |
| Deputy Wood Construction | 6/1/2026 | Conditional Approval | ALEXANDER HANDY |