11907 W RIALTO ST 91352

Certificate Information: 11907 W RIALTO ST 91352

Application / Permit
24014-20000-05665
Plan Check / Job No.
B24VN26677
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 33'-5" X 28'-8" TO EXISTING SINGLE FAMILY DWELLING; ADD 4'-5" X 5' PORCH TO DWELLING; INTERIOR REMODEL; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/6/2025
Issuing Office
Current Status
Issued on 2/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/24/2024 APPLICANT
Assigned to Plan Check Engineer 1/9/2025 SELLA BENYAMIN
Corrections Issued 1/14/2025 SELLA BENYAMIN
Quality Review Completed 1/16/2025 STEVEN KIM
Building Plans Picked Up 1/17/2025 APPLICANT
Plan Check Approved 2/6/2025 SELLA BENYAMIN
Issued 2/6/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/22/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/23/2025 EDGAR ALCARAZ
Sewer availability Cleared 1/23/2025 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/27/2025 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 4/2/2025 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 4/4/2025 Approved DAVID ANDERSON
PLUMBING-Rough 4/21/2025 Partial Approval WILLIAM WREN
Insulation 4/30/2025 Partial Approval NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 5/5/2025 Partial Approval NICHOLAS TROWBRIDGE
Green Building Rough 5/5/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Insulation 5/5/2025 Partial Approval NICHOLAS TROWBRIDGE
MERV13>=Rough 5/5/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 8/27/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 8/27/2025 Approved MATTHEW NELSON
Green Building Rough 8/27/2025 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 8/27/2025 Approved MATTHEW NELSON
MERV13>=Rough 8/27/2025 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 9/18/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/23/2025 Approved MATTHEW NELSON
Underground Mechanical 9/23/2025 Partial Approval MATTHEW NELSON
Insulation 9/29/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/29/2025 Approved MATTHEW NELSON
Drywall Nailing 10/9/2025 Approved MATTHEW NELSON
Shower Pan 12/23/2025 Approved MICHAEL CORTEZ