2907 S HOOVER ST 90007
Certificate Information: 2907 S HOOVER ST 90007
- Application / Permit
- 24014-20000-05653
- Plan Check / Job No.
- B24VN26598
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. 2-story Detached ADU addition to existing 1-story garage per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- CofO Issued on 9/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | JESSE VIDUYA |
| Corrections Issued | 1/3/2025 | JESSE VIDUYA |
| Quality Review Completed | 1/7/2025 | CHAD DOI |
| Applicant returned to address corrections | 2/20/2025 | JESSE VIDUYA |
| Applicant returned to address corrections | 3/12/2025 | JESSE VIDUYA |
| Plan Check Approved | 3/20/2025 | JESSE VIDUYA |
| Issued | 3/20/2025 | APPLICANT |
| CofO in Progress | 9/12/2025 | WILLIAM SIERRA |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
| CofO Issued | 9/13/2025 | DEROLD HAUFF |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2025 | CELINA MORENO |
| Sewer availability | Cleared | 1/17/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 1/30/2025 | CELINA MORENO |
| City Hist. Cultural Monument | Cleared | 2/11/2025 | ERIK VAN BREENE |
| Historic Resource Verification | Cleared | 2/11/2025 | ERIK VAN BREENE |
| Specific Plan | Cleared | 2/11/2025 | ERIK VAN BREENE |
| ZI | Cleared | 2/11/2025 | ERIK VAN BREENE |
| Redevelopment Project Area | Cleared | 2/25/2025 | YASMINE BASHIRI |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | , |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 1752 TEMPLE CITY, CA 91780 |
| Geologist | Minas,, Shant; Lic. No.: EG2607 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 3/28/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 3/28/2025 | Partial Approval | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Partial Inspection | WILLIAM SIERRA |
| Footing/Foundation/Slab | 4/4/2025 | Partial Inspection | WILLIAM SIERRA |
| METHANE-Barrier | 4/4/2025 | Corrections Issued | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 4/7/2025 | Approved | WILLIAM SIERRA |
| METHANE-Barrier | 4/7/2025 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Rough | 5/29/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 5/29/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Rough | 5/30/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Wood Frame | 5/30/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Rough | 6/3/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 6/3/2025 | Conditional Approval | WILLIAM SIERRA |
| Interior/Exterior Lathing | 6/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| PLUMBING-Rough | 6/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 6/5/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| METHANE-Rough | 6/5/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Wood Frame | 6/5/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 6/6/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/6/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/6/2025 | Approved | ENRIQUE MIRELES |
| Wood Frame | 6/6/2025 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/12/2025 | Approved | WILLIAM SIERRA |
| Insulation | 6/12/2025 | Approved | WILLIAM SIERRA |
| METHANE-Rough | 6/12/2025 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 6/16/2025 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 6/16/2025 | Corrections Issued | WILLIAM SIERRA |
| Interior/Exterior Lathing | 6/24/2025 | Partial Approval | WILLIAM SIERRA |
| Sewer | 7/2/2025 | Approved | WILLIAM SIERRA |
| Underground Mechanical | 7/2/2025 | Partial Approval | WILLIAM SIERRA |
| ELECTRICAL-Final | 8/11/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 8/11/2025 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 8/11/2025 | Approved | WILLIAM SIERRA |
| HVAC-Final | 8/11/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 8/11/2025 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Not Required | WILLIAM SIERRA |
| Smoke Detectors | 8/11/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Final | 8/13/2025 | Approved | WILLIAM SIERRA |
| Final | 8/13/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 8/13/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 8/13/2025 | Approved | WILLIAM SIERRA |
| Service/Power Release | 8/13/2025 | Not Required | WILLIAM SIERRA |
| Smoke Detectors | 8/13/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 8/14/2025 | Approved | JUSTIN HAWLEY |
| Final | 8/14/2025 | Corrections Issued | JUSTIN HAWLEY |
| HVAC-Final | 8/14/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 8/14/2025 | Approved | JUSTIN HAWLEY |
| Final | 9/12/2025 | OK to Issue CofO | WILLIAM SIERRA |