4933 N PLACIDIA AVE 91601
Certificate Information: 4933 N PLACIDIA AVE 91601
- Application / Permit
- 24014-20000-05646
- Plan Check / Job No.
- B24VN26532
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE WITH 17'3" X 17'11" IRREG.SHAPED ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) . PER ENGINEER DESIGN.
- Permit Issued
- Issued on 1/28/2025
- Issuing Office
- Current Status
- CofO Issued on 7/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 1/2/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 1/22/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 1/28/2025 | MIROOSH KHACHATOORIAN |
| Issued | 1/28/2025 | APPLICANT |
| CofO in Progress | 6/5/2025 | JAVIER RAMOS JR |
| CofO Issued | 7/23/2025 | RUBEN SALAS |
| Permit Finaled | 7/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/2/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 1/7/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/14/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 1/24/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 1/24/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Vaisman Construction Inc; Lic. No.: 1076712-B | , |
| Engineer | Simonian,, Ara; Lic. No.: C37208 | 314 E BROADWAY STE A GLENDALE, CA 91205 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 2/24/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 2/27/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 3/3/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 3/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 3/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 4/16/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 4/16/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/16/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 4/18/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/18/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 4/18/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 4/23/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/23/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/23/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 4/30/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 5/2/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 5/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 5/9/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 5/13/2025 | Order to Comply Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 5/30/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 5/30/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 5/30/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 6/4/2025 | Approved | JAVIER RAMOS JR |
| Final | 6/4/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 6/4/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 6/4/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 6/4/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/4/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 6/4/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/4/2025 | Approved | JAVIER RAMOS JR |