19024 W SPRAGUE ST 91356

Certificate Information: 19024 W SPRAGUE ST 91356

Application / Permit
24014-20000-05634
Plan Check / Job No.
B24VN26481
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. MAJOR REMODEL AND ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE TO BECOME A 1-STORY SFD WITH ATTACHED TWO (2-CAR) GARAGES DEMO 99% OF (E) STRUCUTRE LEAVING 1'6" WALL WITH ITS FOOTING NFPA 13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 2/18/2025
Issuing Office
Current Status
CofO Issued on 12/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2024 APPLICANT
Assigned to Plan Check Engineer 12/26/2024 JAD BASMA
Corrections Issued 12/29/2024 JAD BASMA
Quality Review Completed 12/31/2024 PRANITA SHAH
Plan Check Approved 2/14/2025 JAD BASMA
Issued 2/18/2025 APPLICANT
CofO in Progress 12/22/2025 SEAN WIRCH
Permit Finaled 12/27/2025 MICHAEL PELHAM
CofO Issued 12/27/2025 MICHAEL PELHAM
Permit Finaled 12/27/2025 MICHAEL PELHAM

Permit Application Clearance Information

Low Impact Development (LID) Cleared 1/6/2025 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 1/7/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 1/7/2025 RYAN CASTRO
Sewer availability Cleared 1/7/2025 RYAN CASTRO
Hydrant and Access approval Cleared 1/23/2025 RUEL COLE
GPI Written Notices Cleared 2/14/2025 JAD BASMA
Grading Pre-Inspection Cleared 2/14/2025 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/1/2025 Approved JOHN KIDWELL
Footing/Foundation/Slab 4/1/2025 Partial Approval JOHN KIDWELL
Underground Mechanical 4/1/2025 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 4/8/2025 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 6/16/2025 Approved JOHN KIDWELL
PLUMBING-Rough 6/16/2025 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Partial Approval JOHN KIDWELL
HVAC-Rough 6/17/2025 Approved JOHN KIDWELL
BUILDING-Rough-Frame 6/18/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 6/18/2025 Not Ready for Inspection JOHN KIDWELL
Gas Test 6/24/2025 Partial Inspection JOHN KIDWELL
Interior/Exterior Lathing 6/24/2025 Partial Approval JOHN KIDWELL
Shower Pan 6/24/2025 Approved JOHN KIDWELL
BUILDING-Rough-Frame 7/2/2025 Approved JOHN KIDWELL
Green Building Rough 7/2/2025 Approved JOHN KIDWELL
Insulation 7/2/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 7/2/2025 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 7/2/2025 Approved JOHN KIDWELL
Drywall Nailing 7/7/2025 Approved JOHN KIDWELL
HVAC-Final 11/10/2025 Corrections Issued HENRY KIM
ELECTRICAL-Final 11/14/2025 Approved JOHN KIDWELL
PLUMBING-Final 11/14/2025 Approved JOHN KIDWELL
Service/Power Release 11/14/2025 Approved JOHN KIDWELL
Final 12/1/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 12/1/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Approved JOHN KIDWELL
Smoke Detectors 12/1/2025 Approved JOHN KIDWELL
Final 12/8/2025 Corrections Issued JOHN KIDWELL
Green Building Final 12/8/2025 Approved JOHN KIDWELL
Final 12/19/2025 OK to Issue CofO JOHN KIDWELL