10649 W CROCKETT ST 91352

Certificate Information: 10649 W CROCKETT ST 91352

Application / Permit
24014-20000-05587
Plan Check / Job No.
B24VN26248
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF (E) DETACHED GARAGE TO (N) ADU PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 1/24/2025
Issuing Office
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2024 APPLICANT
Assigned to Plan Check Engineer 12/24/2024 SERGIO MUNIZ
Corrections Issued 12/25/2024 SERGIO MUNIZ
Plan Check Approved 1/23/2025 SERGIO MUNIZ
Issued 1/24/2025 APPLICANT
CofO in Progress 4/23/2026 DAVID ANDERSON
CofO Issued 5/21/2026 RUBEN SALAS
Permit Finaled 5/21/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/29/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 12/29/2024 RYAN CASTRO
ZA Case Cleared 12/31/2024 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 1/2/2025 RYAN CASTRO
Sewer availability Cleared 1/2/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/20/2025 Corrections Issued DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 7/1/2025 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 7/1/2025 Partial Approval WILLIAM WREN
Excavation/Setback/Form/Re-Bar 7/15/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 7/15/2025 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 9/4/2025 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Partial Approval DAVID ANDERSON
Green Building Rough 9/4/2025 Approved DAVID ANDERSON
HVAC-Rough 9/4/2025 Approved DAVID ANDERSON
MERV13>=Rough 9/4/2025 Approved DAVID ANDERSON
PLUMBING-Rough 9/4/2025 Approved DAVID ANDERSON
Special/Order Compliance 9/4/2025 Corrections Issued DAVID ANDERSON
Deputy Wood Construction 9/8/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 9/16/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 9/16/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Approved DAVID ANDERSON
Sewer 9/16/2025 Partial Approval DAVID ANDERSON
Underground Mechanical 9/16/2025 Partial Approval DAVID ANDERSON
Insulation 9/24/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 9/24/2025 Approved DAVID ANDERSON
Drywall Nailing 10/15/2025 Approved MICHAEL CORTEZ
Service/Power Release 12/11/2025 Corrections Issued DAVID ANDERSON
Final 2/4/2026 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 2/4/2026 Approved DAVID ANDERSON
Green Building Final 2/4/2026 Not Ready for Inspection DAVID ANDERSON
MERV13>=Final 2/4/2026 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Not Required DAVID ANDERSON
Service/Power Release 2/4/2026 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 2/4/2026 Approved DAVID ANDERSON
Final 4/10/2026 Not Ready for Inspection DAVID ANDERSON
Green Building Final 4/10/2026 Approved DAVID ANDERSON
Final 4/22/2026 OK to Issue CofO DAVID ANDERSON