4750 N DEL MORENO PL 91364

Certificate Information: 4750 N DEL MORENO PL 91364

Application / Permit
24014-20000-05576
Plan Check / Job No.
B24VN26205
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: addition to e sfd, full remodeling, kitchen ,bathrooms, demo e poweder room,fire place , demo e kitchen wall
Permit Issued
Issued on 1/15/2025
Issuing Office
Current Status
CofO Issued on 4/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2024 APPLICANT
Assigned to Plan Check Engineer 12/24/2024 JOSEPH RAFOLS
Corrections Issued 12/26/2024 JOSEPH RAFOLS
Plan Check Approved 1/14/2025 JOSEPH RAFOLS
Issued 1/15/2025 APPLICANT
CofO in Progress 11/5/2025 SEAN WIRCH
Permit Finaled 4/13/2026 JOHN JANSON
CofO Issued 4/13/2026 JOHN JANSON
Permit Finaled 4/13/2026 JOHN JANSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/31/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 12/31/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 12/31/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 12/31/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 12/31/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 12/31/2024 BIAINA HARITUNIAN
Sewer availability Cleared 12/31/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 1/6/2025 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 1/7/2025 BIAINA HARITUNIAN
ZA Case Cleared 1/7/2025 JASON CHAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/22/2025 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 1/22/2025 Partial Approval JOHN HAYES
Underground Mechanical 1/22/2025 Corrections Issued JOHN HAYES
Underground Mechanical 1/27/2025 Approved JOHN HAYES
Deputy Drilled-In Anchors 3/3/2025 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 3/5/2025 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/5/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/10/2025 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 3/10/2025 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Approved DAVID SCANTLIN
Footing/Foundation/Slab 3/12/2025 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 4/11/2025 Not Ready for Inspection SEAN WIRCH
HVAC-Rough 4/11/2025 Not Ready for Inspection SEAN WIRCH
Interior/Exterior Lathing 4/11/2025 Not Ready for Inspection SEAN WIRCH
PLUMBING-Rough 4/11/2025 Not Ready for Inspection SEAN WIRCH
Shower Pan 4/11/2025 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 4/16/2025 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 4/16/2025 Not Ready for Inspection JOHN HAYES
HVAC-Rough 4/16/2025 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 4/16/2025 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 4/16/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 4/28/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 4/28/2025 Approved JEFFREY HARTLINE
Green Building Rough 4/28/2025 Approved JEFFREY HARTLINE
HVAC-Rough 4/28/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 4/28/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 4/28/2025 Approved JEFFREY HARTLINE
Special/Order Compliance 4/28/2025 Corrections Issued JEFFREY HARTLINE
Interior/Exterior Lathing 5/1/2025 Partial Approval JOHN COLEMAN
Insulation 5/6/2025 Approved JOHN HAYES
Drywall Nailing 5/13/2025 Approved JOHN COLEMAN
Final 7/1/2025 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 7/1/2025 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Not Ready JOHN HAYES
Smoke Detectors 7/1/2025 Not Ready for Inspection JOHN HAYES
Final 10/23/2025 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Approved JOHN HAYES
Smoke Detectors 10/23/2025 Approved JOHN HAYES
Final 11/4/2025 OK to Issue CofO SEAN WIRCH