8941-8941 1/2 N HASKELL AVE 91343
Certificate Information: 8941-8941 1/2 N HASKELL AVE 91343
- Application / Permit
- 24014-20000-05565
- Plan Check / Job No.
- B24VN26088
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. CONVERT EXISTING ATTACHED CARPORT WITH ADDITION TO NEW ATTACHED ADU PER ORDINANCE
- Permit Issued
- Issued on 1/24/2025
- Issuing Office
- Current Status
- CofO Issued on 4/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2024 | ADAM HEGAZI |
| Corrections Issued | 12/20/2024 | ADAM HEGAZI |
| Plan Check Approved | 1/22/2025 | ADAM HEGAZI |
| No Progress | 1/24/2025 | ADAM HEGAZI |
| Plan Check Approved | 1/24/2025 | ADAM HEGAZI |
| Issued | 1/24/2025 | APPLICANT |
| CofO in Progress | 4/24/2025 | RAUL OLAGI |
| Permit Finaled | 4/25/2025 | RUBEN SALAS |
| CofO Issued | 4/25/2025 | RUBEN SALAS |
| Permit Finaled | 4/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/13/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 1/13/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Ea Constructions Inc; Lic. No.: 1096892-B | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/29/2025 | Partial Inspection | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/5/2025 | Partial Approval | SALVADOR MARTINEZ |
| Sewer | 2/5/2025 | Approved | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 2/6/2025 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 2/10/2025 | Approved | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 2/10/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/3/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/3/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 3/3/2025 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 3/3/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 3/3/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/5/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 3/5/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 3/6/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 3/6/2025 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 3/14/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 3/14/2025 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 3/14/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/21/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 4/21/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 4/21/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 4/21/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 4/21/2025 | Approved | JACK KARGODORIAN |
| HVAC-Final | 4/21/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 4/21/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 4/21/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Gas Company | JACK KARGODORIAN |
| Service/Power Release | 4/21/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 4/21/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 4/23/2025 | Approved | RAUL OLAGI |
| Final | 4/23/2025 | OK to Issue CofO | RAUL OLAGI |