15254 W CLYMER ST 91345

Certificate Information: 15254 W CLYMER ST 91345

Application / Permit
24014-20000-05554
Plan Check / Job No.
B24VN26037
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan - CONVERT THE (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22.A.33(c) AND (d).
Permit Issued
Issued on 1/29/2025
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2024 APPLICANT
Assigned to Plan Check Engineer 12/24/2024 GIOVANNY CHAVEZ
Corrections Issued 12/26/2024 GIOVANNY CHAVEZ
Plan Check Approved 1/28/2025 GIOVANNY CHAVEZ
Issued 1/29/2025 APPLICANT
CofO in Progress 7/8/2025 JENNIFER RABUCHIN
Permit Finaled 7/31/2025 RUBEN SALAS
Permit Finaled 7/31/2025 RUBEN SALAS
CofO Issued 7/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/11/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/11/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/11/2025 CARLOS AGUILERA
Sewer availability Cleared 1/11/2025 CARLOS AGUILERA
Construction near power lines Cleared 1/22/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/6/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/24/2025 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 2/25/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 2/27/2025 Approved JENNIFER RABUCHIN
Sewer 3/5/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 3/5/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/19/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 3/19/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 3/19/2025 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 3/19/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/1/2025 Approved JENNIFER RABUCHIN
Deputy Wood Construction 4/1/2025 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 4/1/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Approved JENNIFER RABUCHIN
Green Building Rough 4/1/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 4/1/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 4/1/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/7/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/7/2025 Approved JENNIFER RABUCHIN
Green Building Rough 4/7/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 4/7/2025 Approved JENNIFER RABUCHIN
Insulation 4/7/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/7/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/7/2025 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 4/10/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/18/2025 Approved JENNIFER RABUCHIN
Service/Power Release 5/6/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 7/1/2025 Not Ready for Inspection JENNIFER RABUCHIN
Final 7/1/2025 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 7/1/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 7/1/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/1/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/1/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/7/2025 Approved JENNIFER RABUCHIN
Final 7/7/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 7/7/2025 Approved JENNIFER RABUCHIN
HVAC-Final 7/7/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/7/2025 Approved JENNIFER RABUCHIN
Service/Power Release 7/7/2025 Approved JENNIFER RABUCHIN