15254 W CLYMER ST 91345
Certificate Information: 15254 W CLYMER ST 91345
- Application / Permit
- 24014-20000-05554
- Plan Check / Job No.
- B24VN26037
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan - CONVERT THE (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22.A.33(c) AND (d).
- Permit Issued
- Issued on 1/29/2025
- Issuing Office
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/24/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 12/26/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 1/28/2025 | GIOVANNY CHAVEZ |
| Issued | 1/29/2025 | APPLICANT |
| CofO in Progress | 7/8/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| CofO Issued | 7/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 1/22/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/6/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/24/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 2/25/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 2/27/2025 | Approved | JENNIFER RABUCHIN |
| Sewer | 3/5/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 3/5/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/19/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 3/19/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 3/19/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/19/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/1/2025 | Approved | JENNIFER RABUCHIN |
| Deputy Wood Construction | 4/1/2025 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 4/1/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/1/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 4/1/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/1/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/7/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 4/10/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/18/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/6/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/1/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 7/1/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 7/1/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 7/1/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/1/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/1/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/7/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 7/7/2025 | Approved | JENNIFER RABUCHIN |