19429 W WELBY WAY 91335

Certificate Information: 19429 W WELBY WAY 91335

Application / Permit
24014-20000-05547
Plan Check / Job No.
B24VN25984
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE WITH ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 2/25/2025
Issuing Office
Current Status
Issued on 2/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/17/2024 APPLICANT
Assigned to Plan Check Engineer 12/26/2024 KAMYAR EMAMI
Building Plans Picked Up 12/27/2024 APPLICANT
Corrections Issued 1/7/2025 KAMYAR EMAMI
Plan Check Approved 2/25/2025 ALEC MOUSAKHANIAN
Issued 2/25/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/13/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/13/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/28/2025 CARLOS AGUILERA
Sewer availability Cleared 1/28/2025 CARLOS AGUILERA
Construction near power lines Cleared 2/13/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/11/2025 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 7/15/2025 Partial Approval ARUTYUN MADATYAN
Sewer 7/15/2025 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 7/17/2025 Partial Approval ARUTYUN MADATYAN
Sewer 7/17/2025 Approved ARUTYUN MADATYAN
Deputy Drilled-In Anchors 7/30/2025 Partial Inspection JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 7/30/2025 Corrections Issued GEVORK IPCHYAN
Footing/Foundation/Slab 8/5/2025 Corrections Issued ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 8/7/2025 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 8/7/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 9/5/2025 Not Ready for Inspection ARUTYUN MADATYAN
Wood Frame 9/5/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 9/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 9/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 9/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 9/18/2025 No Access for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 9/22/2025 No Access for Inspection ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 No Access for Inspection ROBERT GOLD
HVAC-Rough 9/22/2025 No Access for Inspection ROBERT GOLD
PLUMBING-Rough 9/22/2025 No Access for Inspection ROBERT GOLD
Wood Frame 9/22/2025 No Access for Inspection ROBERT GOLD
ELECTRICAL-Rough 9/25/2025 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Partial Approval ARUTYUN MADATYAN
HVAC-Rough 9/25/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 9/25/2025 Approved ARUTYUN MADATYAN
Wood Frame 9/25/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 10/21/2025 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Rough 11/6/2025 Not Ready for Inspection ARUTYUN MADATYAN
Wood Frame 11/6/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 11/10/2025 Partial Approval ROBERT GOLD
ELECTRICAL-Rough 11/10/2025 Approved ROBERT GOLD
Green Building Rough 11/10/2025 Approved ROBERT GOLD
HVAC-Rough 11/10/2025 Approved ROBERT GOLD
Insulation 12/2/2025 Approved ARUTYUN MADATYAN
Shower Pan 12/2/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 12/10/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 12/18/2025 Corrections Issued ARUTYUN MADATYAN
Interior/Exterior Lathing 1/29/2026 Partial Approval ARUTYUN MADATYAN
Interior/Exterior Lathing 2/6/2026 Partial Approval ARUTYUN MADATYAN
Interior/Exterior Lathing 2/10/2026 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 6/1/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 6/1/2026 Not Ready for Inspection ARUTYUN MADATYAN
Final 6/1/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 6/1/2026 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 6/1/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 6/1/2026 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 6/1/2026 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 6/1/2026 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 6/9/2026 Not Ready for Inspection ARUTYUN MADATYAN
Final 6/9/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 6/9/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 6/9/2026 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 6/9/2026 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 6/9/2026 Approved ARUTYUN MADATYAN
Final 6/15/2026 Not Ready for Inspection ARUTYUN MADATYAN