149-149 1/2 W 56TH ST 90037

Certificate Information: 149-149 1/2 W 56TH ST 90037

Application / Permit
24014-20000-05546
Plan Check / Job No.
B24VN25965
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert Existing 1-story 2-Car garage to Detached 2-story (2 units) Accessory Dwelling Units PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g)
Permit Issued
Issued on 5/14/2025
Issuing Office
Current Status
Issued on 5/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/17/2024 APPLICANT
Assigned to Plan Check Engineer 1/2/2025 KHEDER ALRAZAA
Corrections Issued 1/4/2025 KHEDER ALRAZAA
Quality Review Completed 1/16/2025 PRANITA SHAH
Applicant returned to address corrections 3/17/2025 KHEDER ALRAZAA
Applicant returned to address corrections 4/11/2025 KHEDER ALRAZAA
Plan Check Approved 5/14/2025 KHEDER ALRAZAA
Issued 5/14/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/24/2025 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/24/2025 ADRIAN SANCHEZ
Highway dedication Cleared 1/24/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 1/24/2025 ADRIAN SANCHEZ
Sewer availability Cleared 1/24/2025 ADRIAN SANCHEZ
CPC Cleared 2/25/2025 JASON CHAN

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/22/2025 Partial Approval LUIS CASTRO
Deputy Drilled-In Anchors 7/30/2025 Conditional Approval NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 8/4/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 8/4/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 9/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/29/2025 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 10/3/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 10/27/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 10/27/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 10/27/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 10/29/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 10/29/2025 Not Ready for Inspection BARRY HACHE
HVAC-Rough 10/31/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 10/31/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 11/3/2025 Not Ready for Inspection LUIS CASTRO
Interior/Exterior Lathing 11/3/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 11/10/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 11/25/2025 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 12/9/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 12/15/2025 Approved BARRY HACHE
Insulation 12/15/2025 Corrections Issued BARRY HACHE
Insulation 12/22/2025 Approved RAUL BARAJAS
Drywall Nailing 12/29/2025 Approved ALEJANDRO DE ARTOLA
Sewer 3/13/2026 Approved SALVADOR MARTINEZ
Underground Mechanical 3/13/2026 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 3/17/2026 Approved ALEJANDRO DE ARTOLA