6222 N ZELZAH AVE 91316

Certificate Information: 6222 N ZELZAH AVE 91316

Application / Permit
24014-20000-05536
Plan Check / Job No.
B24VN25915
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
13'-4" X 4'-0" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). FIRE SPRINKLER (NFPA-13D) REQUIRED THROUGHOUT.
Permit Issued
Issued on 3/18/2025
Issuing Office
Current Status
CofO Issued on 7/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2024 APPLICANT
Assigned to Plan Check Engineer 12/23/2024 ARTIN ZARUKIAN
Corrections Issued 12/25/2024 ARTIN ZARUKIAN
Building Plans Picked Up 12/30/2024 APPLICANT
Plan Check Approved 3/18/2025 JESSE ARELLANO
Issued 3/18/2025 APPLICANT
CofO in Progress 7/5/2025 JON MCHUGH
Permit Finaled 7/23/2025 DANIEL ORRANTE
CofO Issued 7/23/2025 DANIEL ORRANTE
Permit Finaled 7/23/2025 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/7/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/7/2025 EDGAR ALCARAZ
Sewer availability Cleared 1/7/2025 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 2/21/2025 EDGAR ALCARAZ
ZI Cleared 3/4/2025 MAYELA VILLA
Construction near power lines Cleared 3/17/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/27/2025 Partial Approval MORRIS JACKSON
Sewer 3/27/2025 Approved MORRIS JACKSON
Deputy Drilled-In Anchors 4/1/2025 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 4/2/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 4/21/2025 Corrections Issued JON MCHUGH
PLUMBING-Rough 4/21/2025 Approved JON MCHUGH
Rough-Elec/Plmb/HVAC 4/21/2025 Corrections Issued JON MCHUGH
Verify Sprinkler Sign Off 4/21/2025 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Partial Approval JON MCHUGH
Shower Pan 4/24/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 4/25/2025 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Partial Approval MORRIS JACKSON
Green Building Rough 4/25/2025 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 4/25/2025 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 4/28/2025 Partial Approval JON MCHUGH
Rough-Elec/Plmb/HVAC 4/28/2025 Approved JON MCHUGH
Verify Sprinkler Sign Off 4/28/2025 Approved JON MCHUGH
Interior/Exterior Lathing 4/29/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 5/1/2025 Approved JON MCHUGH
Drywall Nailing 5/1/2025 Approved JON MCHUGH
Green Building Rough 5/1/2025 Approved JON MCHUGH
Insulation 5/1/2025 Approved JON MCHUGH
Final 6/27/2025 Corrections Issued JON MCHUGH
Green Building Final 6/27/2025 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Approved JON MCHUGH
Smoke Detectors 6/27/2025 Approved JON MCHUGH
ELECTRICAL-Final 7/3/2025 Approved JON MCHUGH
Final 7/3/2025 OK to Issue CofO JON MCHUGH
Green Building Final 7/3/2025 Approved JON MCHUGH
HVAC-Final 7/3/2025 Approved JON MCHUGH
PLUMBING-Final 7/3/2025 Approved JON MCHUGH
Service/Power Release 7/3/2025 Approved JON MCHUGH