4605 N TOBIAS AVE 91403

Certificate Information: 4605 N TOBIAS AVE 91403

Application / Permit
24014-20000-05517
Plan Check / Job No.
B24VN25842
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/24/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 SELLA BENYAMIN
Corrections Issued 12/26/2024 SELLA BENYAMIN
Quality Review Completed 12/27/2024 STEVEN KIM
Building Plans Picked Up 1/2/2025 APPLICANT
Plan Check Approved 2/13/2025 SELLA BENYAMIN
Issued 2/24/2025 APPLICANT
No Progress 2/5/2026 RAUL OLAGI
CofO in Progress 2/5/2026 RAUL OLAGI
Permit Finaled 2/17/2026 RUBEN SALAS
CofO Issued 2/17/2026 RUBEN SALAS
Permit Finaled 2/17/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/22/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 1/22/2025 RYAN CASTRO
Sewer availability Cleared 1/22/2025 RYAN CASTRO
ZI Cleared 1/29/2025 JAZMIN ROQUE

Contact Information

Contractor Modern Works Inc; Lic. No.: 1060919-B 13535 VENTURA BLVD SUITE 250      SHERMAN OAKS, CA 91423
Engineer Ilasin,, John Lacebal; Lic. No.: C67469 1011 OARFISH LN      OXNARD, CA 93035

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/7/2025 Corrections Issued MISAEL ESPARZA
Deputy Reinf. Concrete 4/10/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 4/30/2025 Partial Approval MISAEL ESPARZA
Deputy Steel/Welding 5/8/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 6/10/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 6/10/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 6/10/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 6/13/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 6/13/2025 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 6/13/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 7/2/2025 Corrections Issued JOSE AVILA
HVAC-Rough 7/2/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/3/2025 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 7/9/2025 No Access for Inspection NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 7/9/2025 No Access for Inspection NICHOLAS TROWBRIDGE
Green Building Rough 7/9/2025 No Access for Inspection NICHOLAS TROWBRIDGE
MERV13>=Rough 7/9/2025 No Access for Inspection NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 7/10/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Corrections Issued MISAEL ESPARZA
Wood Frame 7/18/2025 Corrections Issued MISAEL ESPARZA
Wood Frame 7/24/2025 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 8/1/2025 Corrections Issued LOUIS ESCOTO
Insulation 8/7/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/7/2025 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 8/15/2025 Conditional Approval MISAEL ESPARZA
Drywall Nailing 8/15/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/15/2025 Approved MISAEL ESPARZA
Sewer 9/4/2025 Partial Inspection MISAEL ESPARZA
ELECTRICAL-Final 1/20/2026 Corrections Issued MISAEL ESPARZA
HVAC-Final 1/20/2026 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 1/20/2026 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 1/26/2026 Approved MISAEL ESPARZA
ELECTRICAL-Final 1/26/2026 Corrections Issued MISAEL ESPARZA
Final 1/26/2026 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 1/26/2026 Approved MISAEL ESPARZA
Green Building Final 1/26/2026 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 1/26/2026 Approved MISAEL ESPARZA
HVAC-Final 1/26/2026 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Final 1/26/2026 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 1/26/2026 Approved MISAEL ESPARZA
PLUMBING-Final 1/26/2026 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/26/2026 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 1/26/2026 Approved MISAEL ESPARZA
ELECTRICAL-Final 2/3/2026 Approved MISAEL ESPARZA
HVAC-Final 2/3/2026 Approved MISAEL ESPARZA
PLUMBING-Final 2/3/2026 Approved MISAEL ESPARZA
Final 2/4/2026 Conditional Approval MISAEL ESPARZA
Green Building Final 2/4/2026 Approved MISAEL ESPARZA
MERV13>=Final 2/4/2026 Approved MISAEL ESPARZA
Service/Power Release 2/11/2026 Approved MISAEL ESPARZA