15813 W STARE ST 91343
Certificate Information: 15813 W STARE ST 91343
- Application / Permit
- 24014-20000-05508
- Plan Check / Job No.
- B24VN25784
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT THE (E) DETACHED GARAGE AND ADDITION TO (N) 44' 11" x 18' IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c)-(d).
- Permit Issued
- Issued on 7/10/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/24/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 12/25/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 3/21/2025 | NAREG ATARIAN |
| Plan Check Approved | 3/26/2025 | NAREG ATARIAN |
| No Progress | 5/26/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/1/2025 | LUISANGEL VALENZUELA |
| Issued | 7/10/2025 | APPLICANT |
| CofO in Progress | 5/27/2026 | CHRISTOPHER ROJAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/19/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2025 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 6/21/2025 | MICHAEL TEMPLE |
| Roof/Waste drainage to street | Cleared | 6/27/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 6/27/2025 | TAL SHEMEN |
| Construction near power lines | Cleared | 6/30/2025 | ENRIQUE ACOSTA |
| Construction within easement | Cleared | 6/30/2025 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Hamsco Construction Co; Lic. No.: 1065709-B | , |
| Engineer | Danialian,, Derik; Lic. No.: C94256 | 15904 INDEX ST. GRANADA HILLS, CA 91344 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/17/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 7/29/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 8/1/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/2/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/9/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 10/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/7/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/7/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/7/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/12/2025 | Approved | CHRISTOPHER ROJAS |
| Grading Pre-Inspection | 11/12/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/12/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/17/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 11/17/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 11/17/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 11/24/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/3/2025 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 12/3/2025 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 2/2/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Sewer | 2/2/2026 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 2/2/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 2/4/2026 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/13/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/13/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/13/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 5/13/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/13/2026 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/13/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/13/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 5/13/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/22/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 5/22/2026 | Partial Approval | CHRISTOPHER ROJAS |
| HVAC-Final | 5/22/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 5/22/2026 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Final | 5/27/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 5/27/2026 | Approved | CHRISTOPHER ROJAS |