15813 W STARE ST 91343

Certificate Information: 15813 W STARE ST 91343

Application / Permit
24014-20000-05508
Plan Check / Job No.
B24VN25784
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT THE (E) DETACHED GARAGE AND ADDITION TO (N) 44' 11" x 18' IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 7/10/2025
Issuing Office
Current Status
CofO in Progress on 5/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/18/2024 APPLICANT
Assigned to Plan Check Engineer 12/24/2024 GIOVANNY CHAVEZ
Corrections Issued 12/25/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 3/21/2025 NAREG ATARIAN
Plan Check Approved 3/26/2025 NAREG ATARIAN
No Progress 5/26/2025 LUISANGEL VALENZUELA
Plan Check Approved 7/1/2025 LUISANGEL VALENZUELA
Issued 7/10/2025 APPLICANT
CofO in Progress 5/27/2026 CHRISTOPHER ROJAS

Permit Application Clearance Information

Address approval Cleared 1/19/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/23/2025 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 6/21/2025 MICHAEL TEMPLE
Roof/Waste drainage to street Cleared 6/27/2025 TAL SHEMEN
Sewer availability Cleared 6/27/2025 TAL SHEMEN
Construction near power lines Cleared 6/30/2025 ENRIQUE ACOSTA
Construction within easement Cleared 6/30/2025 ENRIQUE ACOSTA

Contact Information

Contractor Hamsco Construction Co; Lic. No.: 1065709-B       ,
Engineer Danialian,, Derik; Lic. No.: C94256 15904 INDEX ST.      GRANADA HILLS, CA 91344

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/17/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 7/17/2025 Corrections Issued CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 7/29/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 8/1/2025 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/19/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 10/2/2025 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 10/9/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/17/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 10/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 10/17/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/17/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/7/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 11/7/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/7/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/12/2025 Approved CHRISTOPHER ROJAS
Grading Pre-Inspection 11/12/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 11/12/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/17/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 11/17/2025 Approved CHRISTOPHER ROJAS
Insulation 11/17/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/24/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/3/2025 Approved CHRISTOPHER ROJAS
Shower Pan 12/3/2025 Approved CHRISTOPHER ROJAS
Gas Test 2/2/2026 Partial Approval CHRISTOPHER ROJAS
Sewer 2/2/2026 Approved CHRISTOPHER ROJAS
Underground Mechanical 2/2/2026 Corrections Issued CHRISTOPHER ROJAS
Gas Test 2/4/2026 Approved MATTHEW NELSON
ELECTRICAL-Final 5/13/2026 Corrections Issued JENNIFER RABUCHIN
Final 5/13/2026 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/13/2026 Approved JENNIFER RABUCHIN
Green Building Final 5/13/2026 Approved JENNIFER RABUCHIN
HVAC-Final 5/13/2026 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 5/13/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/13/2026 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 5/13/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/22/2026 Approved CHRISTOPHER ROJAS
Final 5/22/2026 Partial Approval CHRISTOPHER ROJAS
HVAC-Final 5/22/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 5/22/2026 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved CHRISTOPHER ROJAS
Final 5/27/2026 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 5/27/2026 Approved CHRISTOPHER ROJAS