10210 N OAKDALE AVE 91311

Certificate Information: 10210 N OAKDALE AVE 91311

Application / Permit
24014-20000-05491
Plan Check / Job No.
B24VN25711
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(18) Private School
Work Description
eplan Scope of work includes the renovation of the (e) Administration suite at building 1,2,4 to 1 STEM Lab, 1 Science Lab, 1 Prep/Storage room as well as 1 Girls and 1 Boys restroom, and associated hardscape and landscape. There will be an outdoor learning environment east of the classrooms with a trellis and benches. Additionally, scope of work includes the renovation of Devonshire St. staff parking lot including three new EV chargers and the renovation of Oakdale Ave. Parking lot including a new security entry kiosk, three EV chargers, drop off zone, students pedestrian school entry promenade, Chaminade Hall entry canopy and associated hardscape and landscape.
Permit Issued
Issued on 6/12/2025
Issuing Office
Current Status
Issued on 6/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/16/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 QUAN NGHIEM
Assigned to Zoning Architect 12/19/2024 MEGAN KOLP
Corrections Issued 12/27/2024 QUAN NGHIEM
Quality Review Completed 12/30/2024 PETER KIM
Applicant returned to address corrections 4/7/2025 QUAN NGHIEM
Applicant returned to address corrections 4/10/2025 QUAN NGHIEM
Applicant returned to address corrections 4/22/2025 QUAN NGHIEM
Applicant returned to address corrections 4/23/2025 QUAN NGHIEM
Plan Check Approved 6/12/2025 QUAN NGHIEM
Issued 6/12/2025 APPLICANT
TCO Issued (Expire Date: 03-30-2026) 10/1/2025 JEFFREY DURAN

Permit Application Clearance Information

ZA Case Cleared 1/21/2025 ASHLEY RODARTE
ZA Case Cleared 1/21/2025 ASHLEY RODARTE
ZA Case Cleared 1/21/2025 ASHLEY RODARTE
ZA Case Cleared 1/21/2025 ASHLEY RODARTE
Roof/Waste drainage to street Cleared 1/25/2025 CARLOS AGUILERA
Sewer availability Cleared 1/25/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/27/2025 CARLOS AGUILERA
Green Code Cleared 3/28/2025 MICHAEL AYERS
Fire Marshal Fire Life Safety Cleared 4/15/2025 DOMINIQUE MEDINA
Frnt yard landscape/Water mgmt Cleared 4/18/2025 DANIEL CORONADO
Prkng lot landscape/Water mgmt Cleared 4/18/2025 DANIEL CORONADO
ZA Case Cleared 4/18/2025 DANIEL CORONADO
DAS Clearance Cleared 5/19/2025 Jesse Arellano
Zoning Plan Check Cleared 6/11/2025 MEGAN KOLP
Low Impact Development (LID) Cleared 6/12/2025 MITESH PATEL

Contact Information

Architect Rabadi,, Hazim Jalal; Lic. No.: NA29074       ,
Contractor B N Builders Inc; Lic. No.: 799131-B 2601 4TH AVE 350      SEATTLE, WA 98121
Engineer Pearson,, James Dale; Lic. No.: S4335 413 S GRAND OAKS AVE      PASADENA, CA 91107

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 7/11/2025 Conditional Approval DEANDRE HOFFMAN
Green Building Rough 7/11/2025 Partial Inspection DEANDRE HOFFMAN
Piling/Pier/Caisson 7/11/2025 Partial Inspection DEANDRE HOFFMAN
Wood Frame 7/11/2025 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 7/15/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 7/16/2025 Conditional Approval JEFFREY DURAN
Piling/Pier/Caisson 7/16/2025 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 7/17/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 7/18/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 7/24/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 7/25/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 7/25/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 7/28/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 7/29/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 7/30/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 7/30/2025 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 7/30/2025 Partial Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 7/31/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 7/31/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/1/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 8/1/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/4/2025 Conditional Approval GREGORY POMISH
Piling/Pier/Caisson 8/5/2025 Not Ready for Inspection DEANDRE HOFFMAN
Deputy Other (see comments) 8/8/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/8/2025 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 8/11/2025 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/12/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/13/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/14/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/15/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/20/2025 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/21/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/27/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/28/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 9/3/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 9/10/2025 Conditional Approval JEFFREY DURAN
Special/Order Compliance 9/19/2025 Approved DEANDRE HOFFMAN
Deputy Reinf. Concrete 9/29/2025 Conditional Approval DEANDRE HOFFMAN
Light Gage Steel Frame 10/30/2025 Partial Approval KENNETH ROBERTS
Deputy Reinf. Concrete 10/31/2025 Conditional Approval JEFFREY DURAN
Pre-Inspection 11/20/2025 Partial Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 12/11/2025 Partial Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 12/12/2025 Conditional Approval DEANDRE HOFFMAN
Piling/Pier/Caisson 12/15/2025 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 12/16/2025 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 12/17/2025 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/19/2025 Conditional Approval JEFFREY DURAN
Structural Steel Frame 1/9/2026 Partial Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 1/14/2026 Conditional Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 1/14/2026 Partial Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 1/14/2026 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 1/15/2026 Conditional Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 1/15/2026 Not Ready for Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 1/16/2026 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 1/21/2026 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 1/23/2026 Conditional Approval JEFFREY DURAN
Piling/Pier/Caisson 1/23/2026 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/26/2026 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/29/2026 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 2/6/2026 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/9/2026 Conditional Approval JEFFREY DURAN
Green Building Rough 2/25/2026 Partial Inspection EDWIN GREGORYONA
Wood Frame 2/25/2026 Partial Inspection EDWIN GREGORYONA
Deputy Drilled-In Anchors 2/26/2026 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 2/26/2026 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 3/3/2026 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 3/9/2026 Partial Approval EDWIN GREGORYONA
Green Building Rough 3/9/2026 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 3/9/2026 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 3/12/2026 Partial Inspection GREGORY POMISH
Wood Frame 3/12/2026 Partial Approval GREGORY POMISH
Insulation 3/13/2026 Not Ready for Inspection EDWIN GREGORYONA
Insulation 3/17/2026 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/20/2026 Partial Approval EDWIN GREGORYONA
Green Building Rough 3/20/2026 Partial Inspection EDWIN GREGORYONA
Wood Frame 3/20/2026 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/25/2026 Partial Inspection EDWIN GREGORYONA
Green Building Rough 3/25/2026 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 3/27/2026 Partial Inspection EDWIN GREGORYONA
Green Building Rough 3/27/2026 Partial Inspection EDWIN GREGORYONA
Wood Frame 4/6/2026 Partial Approval EDWIN GREGORYONA
Insulation 4/10/2026 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 5/6/2026 Approved EDWIN GREGORYONA
Deputy Drilled-In Anchors 6/3/2026 Conditional Approval JEFFREY DURAN
Drywall Nailing 6/10/2026 Approved EDWIN GREGORYONA
Final 6/10/2026 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 6/10/2026 Approved EDWIN GREGORYONA
Green Building Final 6/10/2026 Approved EDWIN GREGORYONA
Green Building Rough 6/10/2026 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 6/10/2026 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 6/10/2026 Approved EDWIN GREGORYONA
Wood Frame 6/10/2026 Approved EDWIN GREGORYONA
Final 6/23/2026 Not Ready for Inspection EDWIN GREGORYONA
Final 7/9/2026 Not Ready for Inspection EDWIN GREGORYONA