7928-7930 N DRISCOLL AVE 91406

Certificate Information: 7928-7930 N DRISCOLL AVE 91406

Application / Permit
24014-20000-05483
Plan Check / Job No.
B24VN25651
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Convert (E) attached garage to Accessory Dwelling Unit w/ addition per LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 3/24/2025
Issuing Office
Current Status
CofO Issued on 12/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2024 APPLICANT
Assigned to Plan Check Engineer 12/17/2024 AMY GUEVARRA
Corrections Issued 12/23/2024 AMY GUEVARRA
Applicant returned to address corrections 1/16/2025 REZA HAGHIGHAT
Applicant returned to address corrections 1/21/2025 AMY GUEVARRA
Applicant returned to address corrections 1/27/2025 AMY GUEVARRA
Plan Check Approved 1/31/2025 AMY GUEVARRA
Issued 3/24/2025 APPLICANT
CofO in Progress 12/3/2025 GAREN HAYRAPETYAN
Permit Finaled 12/9/2025 RUBEN SALAS
CofO Issued 12/9/2025 RUBEN SALAS
Permit Finaled 12/9/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/28/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 12/28/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/2/2025 RYAN CASTRO
Sewer availability Cleared 1/2/2025 RYAN CASTRO

Contact Information

Contractor Gabor Design Group Inc The; Lic. No.: 842370-B       ,
Engineer Villanueva,, Vernon Nipal; Lic. No.: C74117 500 E CARSON PLAZA DR, SUITE 217      CARSON, CA 90746

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/25/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/1/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 5/9/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 5/20/2025 Partial Approval JACK KARGODORIAN
Wood Frame 5/20/2025 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/3/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 7/3/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 7/9/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 7/9/2025 Corrections Issued SALVADOR MARTINEZ
Shower Pan 7/9/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 7/14/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/14/2025 Approved NICHOLAS TROWBRIDGE
Shower Pan 7/14/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 7/15/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 7/15/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/18/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 7/18/2025 Approved GAREN HAYRAPETYAN
Insulation 7/30/2025 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 8/4/2025 Conditional Approval MICHAEL CORTEZ
Insulation 8/4/2025 Conditional Approval MICHAEL CORTEZ
Final 10/28/2025 Corrections Issued GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/28/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 10/28/2025 Approved GAREN HAYRAPETYAN
Final 12/3/2025 OK to Issue CofO GAREN HAYRAPETYAN