7517 N NEWCASTLE AVE 91335
Certificate Information: 7517 N NEWCASTLE AVE 91335
- Application / Permit
- 24014-20000-05471
- Plan Check / Job No.
- B24VN25573
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION BETWEEN GARAGE AND SINGLE FAMILY DWELLING TO MAKE ONE STRUCTURE. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Current Status
- CofO Issued on 9/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | PINANK PATEL |
| Corrections Issued | 12/20/2024 | PINANK PATEL |
| Building Plans Picked Up | 1/9/2025 | APPLICANT |
| Plan Check Approved | 1/17/2025 | ISIS ARGUETA |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 8/25/2025 | JUAN ALVARADO |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
| CofO Issued | 9/6/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/30/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Excavation/Setback/Form/Re-Bar | 2/27/2025 | Approved | JUAN ALVARADO |
| Wood Frame | 3/12/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Wood Frame | 3/18/2025 | Approved | JUAN ALVARADO |
| Wood Frame | 5/30/2025 | Partial Approval | JUAN ALVARADO |
| HVAC-Rough | 6/9/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Interior/Exterior Lathing | 6/9/2025 | Corrections Issued | JUAN ALVARADO |
| BUILDING-Rough-Frame | 6/12/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 6/12/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 6/12/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 6/12/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 6/12/2025 | Approved | JUAN ALVARADO |
| Insulation | 6/17/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 6/26/2025 | Approved | JEFFREY PARD |
| Final | 8/18/2025 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 8/18/2025 | Approved | JUAN ALVARADO |
| Green Building Final | 8/18/2025 | Approved | JUAN ALVARADO |
| HVAC-Final | 8/18/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 8/18/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 8/18/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 8/22/2025 | Approved | JUAN ALVARADO |
| Final | 8/22/2025 | OK to Issue CofO | JUAN ALVARADO |