7414 N RANCHITO AVE 91405

Certificate Information: 7414 N RANCHITO AVE 91405

Application / Permit
24014-20000-05460
Plan Check / Job No.
B24VN25529
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Addition to and conversion of (E) detached garage into an ADU per Ordinance (LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 1/15/2025
Issuing Office
Current Status
CofO Issued on 10/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2024 APPLICANT
Assigned to Plan Check Engineer 12/16/2024 HOOMAN HAJIZADEH
Corrections Issued 12/17/2024 HOOMAN HAJIZADEH
Applicant returned to address corrections 12/27/2024 NGHI SU
Applicant returned to address corrections 1/2/2025 SUNMIN LEE
Applicant returned to address corrections 1/11/2025 SUNMIN LEE
Plan Check Approved 1/14/2025 SUNMIN LEE
Issued 1/15/2025 APPLICANT
CofO in Progress 9/25/2025 VINCENT HANLEY
CofO Issued 10/16/2025 RUBEN SALAS
Permit Finaled 10/16/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 12/19/2024 WALTER RAMIREZ
Address approval Cleared 12/24/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 12/24/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 12/31/2024 CARLOS RAMIREZ
Sewer availability Cleared 12/31/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/29/2025 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 2/4/2025 Approved MATTHEW NELSON
Deputy Wood Construction 2/20/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2025 Approved VINCENT HANLEY
HVAC-Rough 3/24/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Final 3/24/2025 Approved VINCENT HANLEY
Wood Frame 3/24/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 5/5/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/5/2025 Approved VINCENT HANLEY
Green Building Rough 5/5/2025 Approved VINCENT HANLEY
HVAC-Rough 5/5/2025 Approved VINCENT HANLEY
Underground Mechanical 5/5/2025 Partial Approval VINCENT HANLEY
Insulation 5/14/2025 Approved DAVID MATSON
Drywall Nailing 5/20/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/17/2025 Approved LOUIS ESCOTO
Shower Pan 6/17/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 9/8/2025 Corrections Issued VINCENT HANLEY
Final 9/8/2025 Corrections Issued VINCENT HANLEY
Green Building Final 9/8/2025 Approved VINCENT HANLEY
PLUMBING-Final 9/8/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/8/2025 SGSOV Approved VINCENT HANLEY
Smoke Detectors 9/8/2025 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 9/24/2025 Approved VINCENT HANLEY
Final 9/24/2025 OK to Issue CofO VINCENT HANLEY
HVAC-Final 9/24/2025 Approved VINCENT HANLEY
Smoke Detectors 9/24/2025 Approved VINCENT HANLEY