11921 N GOTHIC AVE 91344

Certificate Information: 11921 N GOTHIC AVE 91344

Application / Permit
24014-20000-05453
Plan Check / Job No.
B24VN25494
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 56'-3" X 24' TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINLERS THROUGHOUT
Permit Issued
Issued on 1/14/2025
Issuing Office
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 SELLA BENYAMIN
Corrections Issued 12/26/2024 SELLA BENYAMIN
Quality Review Completed 12/27/2024 STEVEN KIM
Building Plans Picked Up 12/30/2024 APPLICANT
Plan Check Approved 1/14/2025 SELLA BENYAMIN
Issued 1/14/2025 APPLICANT
CofO in Progress 3/20/2026 CHRISTOPHER ROJAS
Permit Finaled 4/16/2026 RUBEN SALAS
CofO Issued 4/16/2026 RUBEN SALAS
Permit Finaled 4/16/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/2/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/2/2025 BIAINA HARITUNIAN
Sewer availability Cleared 1/2/2025 BIAINA HARITUNIAN
GPI Written Notices Cleared 1/14/2025 SELLA BENYAMIN
Grading Pre-Inspection Cleared 1/14/2025 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 17770 CAPE JASMINE RD      CANYON COUNTRY, CA 91387

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/4/2025 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 6/4/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/4/2025 Partial Approval CHRISTOPHER ROJAS
Deputy Wood Construction 6/6/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 6/12/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 6/12/2025 Corrections Issued CHRISTOPHER ROJAS
Deputy Wood Construction 8/19/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 8/25/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 8/25/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 8/25/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 8/25/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/3/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 9/3/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/9/2025 Partial Approval CHRISTOPHER ROJAS
Special/Order Compliance 9/9/2025 Partial Inspection RAUL OLAGI
Insulation 9/25/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 10/3/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/3/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 3/9/2026 Corrections Issued CHRISTOPHER ROJAS
Final 3/9/2026 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/9/2026 Approved CHRISTOPHER ROJAS
Green Building Final 3/9/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 3/9/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 3/9/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 3/9/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 3/17/2026 Corrections Issued CHRISTOPHER ROJAS
Final 3/17/2026 Corrections Issued CHRISTOPHER ROJAS
Final 3/20/2026 OK to Issue CofO CHRISTOPHER ROJAS