4621 N WILLOW CREST AVE 91602
Certificate Information: 4621 N WILLOW CREST AVE 91602
- Application / Permit
- 24014-20000-05445
- Plan Check / Job No.
- B24VN25445
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel to (E) 1 Story SFD
- Permit Issued
- Issued on 4/25/2025
- Issuing Office
- Current Status
- CofO Issued on 11/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | HERNAN ARREOLA |
| Corrections Issued | 1/8/2025 | HERNAN ARREOLA |
| Quality Review Completed | 1/9/2025 | PETER KIM |
| Plan Check Approved | 3/12/2025 | HERNAN ARREOLA |
| Issued | 4/25/2025 | APPLICANT |
| CofO in Progress | 9/22/2025 | JAVIER RAMOS JR |
| Permit Finaled | 11/19/2025 | RUBEN SALAS |
| CofO Issued | 11/19/2025 | RUBEN SALAS |
| Permit Finaled | 11/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/13/2025 | KEVIN CHUNG |
| Sewer availability | Cleared | 2/13/2025 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2025 | KEVIN CHUNG |
Contact Information
| Contractor | Pacific Ocean Builders Inc; Lic. No.: 1077872-B | , |
| Engineer | Mirpoor,, Waheed Ahmad; Lic. No.: C94801 | 555 ROSEWOOD AVE APT#308 CAMARILLO, CA 93010 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/6/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/15/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/15/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/17/2025 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/17/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 7/17/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/17/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 7/17/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/21/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 7/25/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/25/2025 | Approved | JOSE AVILA |
| Sewer | 7/25/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 7/31/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/18/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/18/2025 | Approved | JAVIER RAMOS JR |
| Green Building Final | 9/18/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 9/18/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 9/18/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 9/22/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/22/2025 | OK to Issue CofO | JAVIER RAMOS JR |