4555 1/2 N WILLOW CREST AVE 91602

Certificate Information: 4555 1/2 N WILLOW CREST AVE 91602

Application / Permit
24014-20000-05425
Plan Check / Job No.
B24VN25298
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 2-STORY DETACHED ACCESSORY DWELLING UNIT WITH 10'-0" x 16'-6" ADDITION AT 2ND FLOOR AND CARPORT BELOW TO CREATE A 2-STORY IRREGULAR SHAPED 47'-4" x 22'-6" 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT WITH ATTACHED 1- CAR CARPORT PER ENGINEERING
Permit Issued
Issued on 1/14/2025
Issuing Office
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 ALFRED RAMIREZ
Corrections Issued 12/14/2024 ALFRED RAMIREZ
Quality Review Completed 12/17/2024 STEVEN KIM
Building Plans Picked Up 12/18/2024 APPLICANT
Plan Check Approved 1/14/2025 ALFRED RAMIREZ
Issued 1/14/2025 APPLICANT
CofO in Progress 11/21/2025 JAVIER RAMOS JR
Permit Finaled 12/31/2025 RUBEN SALAS
CofO Issued 12/31/2025 RUBEN SALAS
Permit Finaled 12/31/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/2/2025 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 1/2/2025 EDGAR ALCARAZ
Sewer availability Cleared 1/2/2025 EDGAR ALCARAZ
Senate Bill 9 Cleared 1/3/2025 ASHLEY RODARTE

Contact Information

Contractor Owner-Builder       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/6/2025 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 2/19/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 2/19/2025 Approved CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 2/26/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/4/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 4/4/2025 Approved JAVIER RAMOS JR
HVAC-Rough 4/4/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/4/2025 Approved JAVIER RAMOS JR
Insulation 5/6/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/6/2025 Partial Approval JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/23/2025 SGSOV Not Ready WILLIAM WREN
BUILDING-Rough-Frame 10/31/2025 Approved JAVIER RAMOS JR
Drywall Nailing 10/31/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 10/31/2025 Approved JAVIER RAMOS JR
Final 10/31/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 10/31/2025 Approved JAVIER RAMOS JR
Green Building Rough 10/31/2025 Approved JAVIER RAMOS JR
MERV13>=Final 10/31/2025 Approved JAVIER RAMOS JR
MERV13>=Rough 10/31/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 10/31/2025 Approved JAVIER RAMOS JR
Final 11/21/2025 OK to Issue CofO JAVIER RAMOS JR