7541 N ORION AVE 91406

Certificate Information: 7541 N ORION AVE 91406

Application / Permit
24014-20000-05397
Plan Check / Job No.
B24VN25096
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 2-CAR GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d), EXPAND 1ST & ADD 2ND STORY **ePlan**
Permit Issued
Issued on 3/4/2025
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 NILOOFAR MEHRAIN
Corrections Issued 12/24/2024 NILOOFAR MEHRAIN
Quality Review Completed 1/2/2025 JASON HEALEY
Applicant returned to address corrections 2/12/2025 NILOOFAR MEHRAIN
Plan Check Approved 2/27/2025 NILOOFAR MEHRAIN
Issued 3/4/2025 APPLICANT
CofO in Progress 10/23/2025 VINCENT HANLEY
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/6/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/6/2025 LEE GUILBEAUX
Address approval Cleared 1/7/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/7/2025 LEE GUILBEAUX
Sewer availability Cleared 1/7/2025 LEE GUILBEAUX
Construction near power lines Cleared 1/29/2025 GEVORK KARAPETYAN
Construction within easement Cleared 1/29/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/19/2025 Approved VINCENT HANLEY
PLUMBING-Rough 4/7/2025 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 4/10/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/11/2025 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 4/15/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 5/7/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/7/2025 Partial Approval VINCENT HANLEY
Green Building Rough 5/7/2025 Not Ready for Inspection VINCENT HANLEY
MERV13>=Rough 5/7/2025 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 5/20/2025 Approved VINCENT HANLEY
Sewer 5/20/2025 Approved VINCENT HANLEY
Underground Mechanical 5/20/2025 Partial Approval VINCENT HANLEY
Gas Test 5/28/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 6/11/2025 Approved VINCENT HANLEY
HVAC-Rough 6/11/2025 Approved VINCENT HANLEY
Underground Mechanical 6/11/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/23/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Approved VINCENT HANLEY
Green Building Rough 6/23/2025 Approved VINCENT HANLEY
MERV13>=Rough 6/23/2025 Approved VINCENT HANLEY
Insulation 7/7/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/7/2025 Partial Approval VINCENT HANLEY
Drywall Nailing 7/15/2025 Approved MICHAEL CORTEZ
Shower Pan 7/21/2025 Approved AMY COLIN
Interior/Exterior Lathing 7/22/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 9/18/2025 Approved VINCENT HANLEY
Final 9/18/2025 Corrections Issued VINCENT HANLEY
HVAC-Final 9/18/2025 Approved VINCENT HANLEY
PLUMBING-Final 9/18/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/10/2025 Approved VINCENT HANLEY
Final 10/10/2025 Partial Approval VINCENT HANLEY
Green Building Final 10/10/2025 Approved VINCENT HANLEY
MERV13>=Final 10/10/2025 Approved VINCENT HANLEY
Service/Power Release 10/10/2025 Approved VINCENT HANLEY
Smoke Detectors 10/10/2025 Approved VINCENT HANLEY
Final 10/23/2025 OK to Issue CofO VINCENT HANLEY