7541 N ORION AVE 91406
Certificate Information: 7541 N ORION AVE 91406
- Application / Permit
- 24014-20000-05397
- Plan Check / Job No.
- B24VN25096
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2-CAR GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d), EXPAND 1ST & ADD 2ND STORY **ePlan**
- Permit Issued
- Issued on 3/4/2025
- Issuing Office
- Current Status
- CofO Issued on 11/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/24/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/2/2025 | JASON HEALEY |
| Applicant returned to address corrections | 2/12/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 2/27/2025 | NILOOFAR MEHRAIN |
| Issued | 3/4/2025 | APPLICANT |
| CofO in Progress | 10/23/2025 | VINCENT HANLEY |
| CofO Issued | 11/13/2025 | RUBEN SALAS |
| Permit Finaled | 11/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/6/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/6/2025 | LEE GUILBEAUX |
| Address approval | Cleared | 1/7/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/7/2025 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 1/29/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 1/29/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/19/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/7/2025 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 4/10/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/11/2025 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 4/15/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/7/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 5/7/2025 | Not Ready for Inspection | VINCENT HANLEY |
| MERV13>=Rough | 5/7/2025 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 5/20/2025 | Approved | VINCENT HANLEY |
| Sewer | 5/20/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 5/20/2025 | Partial Approval | VINCENT HANLEY |
| Gas Test | 5/28/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/11/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/11/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 6/11/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/23/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/23/2025 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 6/23/2025 | Approved | VINCENT HANLEY |
| Insulation | 7/7/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/7/2025 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 7/15/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 7/21/2025 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 7/22/2025 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 9/18/2025 | Approved | VINCENT HANLEY |
| Final | 9/18/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 9/18/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/18/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/10/2025 | Approved | VINCENT HANLEY |
| Final | 10/10/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Final | 10/10/2025 | Approved | VINCENT HANLEY |
| MERV13>=Final | 10/10/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 10/10/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 10/10/2025 | Approved | VINCENT HANLEY |
| Final | 10/23/2025 | OK to Issue CofO | VINCENT HANLEY |