328 N VAN NESS AVE 90004

Certificate Information: 328 N VAN NESS AVE 90004

Application / Permit
24014-20000-05396
Plan Check / Job No.
B24VN25074
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 19'-5" X 15'-7" PORTION OF EXISTING GARAGE AND ADD 6' X 19'-5" AT 1ST FLOOR AND ADD 19'-5" X 20'-5" AT 2ND FLOOR TO CREATE (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). CONVERT 2' X 19'-5" PORTION OF GARAGE TO VOID SPACE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/5/2025
Issuing Office
Current Status
CofO Issued on 8/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 RAPHAEL ROSAS
Corrections Issued 12/17/2024 RAPHAEL ROSAS
Quality Review Completed 12/17/2024 STEVEN KIM
Building Plans Picked Up 12/18/2024 APPLICANT
Applicant returned to address corrections 1/15/2025 RAPHAEL ROSAS
Plan Check Approved 3/5/2025 RAPHAEL ROSAS
Issued 3/5/2025 APPLICANT
CofO in Progress 8/14/2025 JEFFREY MEAD
Permit Finaled 8/16/2025 DEROLD HAUFF
CofO Issued 8/16/2025 DEROLD HAUFF
Permit Finaled 8/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/2/2025 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 1/2/2025 JESSICA OPINION
Roof/Waste drainage to street Cleared 1/2/2025 JESSICA OPINION
Sewer availability Cleared 1/2/2025 JESSICA OPINION
Construction near power lines Cleared 2/24/2025 RIDWAN HARDY

Contact Information

Contractor Trinity Builders & Design Inc; Lic. No.: 988119-B 7022 DARBY AVE UNIT A      RESEDA, CA 91335
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2025 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Conditional Approval JEFFREY MEAD
HVAC-Rough 5/22/2025 Approved JEFFREY MEAD
PLUMBING-Rough 5/22/2025 Approved JEFFREY MEAD
BUILDING-Rough-Frame 5/28/2025 Approved JEFFREY MEAD
ELECTRICAL-Rough 5/28/2025 Approved JEFFREY MEAD
Green Building Rough 5/28/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 5/28/2025 Partial Approval JEFFREY MEAD
Shower Pan 5/28/2025 Approved JEFFREY MEAD
Insulation 5/30/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 5/30/2025 Approved JOSH MEISTER
Drywall Nailing 6/3/2025 Approved JOSH MEISTER
ELECTRICAL-Final 8/5/2025 Approved JEFFREY MEAD
Final 8/5/2025 Corrections Issued JEFFREY MEAD
Green Building Final 8/5/2025 Approved JEFFREY MEAD
HVAC-Final 8/5/2025 Approved JEFFREY MEAD
PLUMBING-Final 8/5/2025 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Approved JEFFREY MEAD
Smoke Detectors 8/5/2025 Approved JEFFREY MEAD
Final 8/13/2025 OK to Issue CofO JEFFREY MEAD