1300 5/8-3/4 W 57TH ST 90037
Certificate Information: 1300 5/8-3/4 W 57TH ST 90037
- Application / Permit
- 24014-20000-05394
- Plan Check / Job No.
- B24VN24264
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT PORTION OF EXISTING GARAGE WITH ADDITION INTO A 2-STORY (26'-9" X 19') TWO ACCESSORY DWELLING UNITS PER GC 66323(a)(4) ON WEST SIDE OF LOT
- Permit Issued
- Issued on 7/28/2025
- Issuing Office
- Current Status
- Issued on 7/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 12/8/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 12/11/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 4/30/2025 | VAHAN JIVALAGIAN |
| Plan Check Approved | 6/10/2025 | VAHAN JIVALAGIAN |
| Plan Check Approved | 7/15/2025 | VAHAN JIVALAGIAN |
| Issued | 7/28/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/3/2025 | CHRISTINA BRACO |
| Address approval | Cleared | 2/11/2025 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2025 | CHRISTINA BRACO |
| Sewer availability | Cleared | 2/13/2025 | CHRISTINA BRACO |
| Community Plan Implem. Overlay | Cleared | 3/3/2025 | MANERI ROMAN |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: C37588 | 1801 S FAIRFAX AVE LOS ANGELES, CA 90019 |
| Architect | Mcvay,, Bruce Cameron; Lic. No.: C11870 | 6440 E. EL ROBLE STREET LONG BEACH, CA 90815 |
| Contractor | Money Talks Inc; Lic. No.: 1133578-B | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/4/2025 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 8/4/2025 | Not Ready for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 8/5/2025 | Corrections Issued | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 8/7/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/18/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 8/20/2025 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/25/2025 | Approved | BRENDAN MORELLI |
| Pre-Inspection | 9/2/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Partial Approval | LUIS CASTRO |
| Wood Frame | 9/19/2025 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2025 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/26/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 12/2/2025 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 12/2/2025 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 12/8/2025 | Approved | SABAS ALONSO |
| Insulation | 12/12/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 12/18/2025 | Approved | ALEX COLIN |
| Sewer | 2/6/2026 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 7/21/2026 | Approved | SABAS ALONSO |