11820 W MISSOURI AVE 90025

Certificate Information: 11820 W MISSOURI AVE 90025

Application / Permit
24014-20000-05387
Plan Check / Job No.
B24VN25015
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
9'-0" X 18'-0" IRREGULAR SHAPED ADDITION TO (E) GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 1/28/2025
Issuing Office
Current Status
CofO Issued on 6/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2024 APPLICANT
Assigned to Plan Check Engineer 12/13/2024 ARTIN ZARUKIAN
Corrections Issued 12/14/2024 ARTIN ZARUKIAN
Building Plans Picked Up 12/17/2024 APPLICANT
Applicant returned to address corrections 1/22/2025 GIOVANNY CHAVEZ
Plan Check Approved 1/28/2025 YAQUB MIRZA
Issued 1/28/2025 APPLICANT
CofO in Progress 6/12/2025 ARAM AVEDISIAN
Permit Finaled 6/17/2025 RICHARD STEINBACH
CofO Issued 6/17/2025 RICHARD STEINBACH
Permit Finaled 6/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/10/2025 DARIN LAM
Roof/Waste drainage to street Cleared 1/10/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 1/13/2025 DARIN LAM
Sewer availability Cleared 1/13/2025 DARIN LAM
Construction near power lines Cleared 1/15/2025 WALTER RAMIREZ
Permit Cleared 1/21/2025 HISASHI KOBAYAKAWA
Specific Plan Cleared 1/27/2025 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/27/2025 Approved KIRK SANDERS
Footing/Foundation/Slab 2/27/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 2/27/2025 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 2/27/2025 Approved KIRK SANDERS
Footing/Foundation/Slab 3/5/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 3/28/2025 Partial Approval KIRK SANDERS
ELECTRICAL-Final 3/28/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 3/28/2025 Approved KIRK SANDERS
HVAC-Rough 3/28/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 3/28/2025 Approved KIRK SANDERS
HVAC-Rough 4/3/2025 Approved KIRK SANDERS
Insulation 4/3/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 4/4/2025 Partial Approval KIRK SANDERS
Special/Order Compliance 4/4/2025 Corrections Issued KIRK SANDERS
Drywall Nailing 4/11/2025 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Corrections Issued KIRK SANDERS
Green Building Rough 4/11/2025 Approved KIRK SANDERS
Shower Pan 4/11/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 4/14/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 4/14/2025 Approved KIRK SANDERS
Drywall Nailing 5/21/2025 Approved KIRK SANDERS
ELECTRICAL-Final 5/21/2025 Corrections Issued KIRK SANDERS
Final 5/21/2025 Corrections Issued KIRK SANDERS
Green Building Final 5/21/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Final 5/21/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 5/21/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Gas Company KIRK SANDERS
Smoke Detectors 5/21/2025 Approved KIRK SANDERS
ELECTRICAL-Final 5/28/2025 Corrections Issued KIRK SANDERS
Final 5/28/2025 Not Ready for Inspection KIRK SANDERS
Green Building Final 5/28/2025 Approved KIRK SANDERS
HVAC-Final 5/28/2025 Approved KIRK SANDERS
PLUMBING-Final 5/28/2025 Approved KIRK SANDERS
Final 6/2/2025 Partial Approval KIRK SANDERS
Final 6/12/2025 OK to Issue CofO ARAM AVEDISIAN