2929-2931 S CARDIFF AVE 90034

Certificate Information: 2929-2931 S CARDIFF AVE 90034

Application / Permit
24014-20000-05385
Plan Check / Job No.
B24VN24992
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVING ALL OF THE EXISTING DWELLING EXCEPT FOR 1 SF OF FOOTING TO REMAIN IN THE REAR OF THE BUILDING AND REPLACE WITH NEW 1ST FLOOR (1,182.95 SF) WITH 2ND FLOOR (1,699.55 SF) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE (342 SF) AND ACCESSORY DWELLING UNIT LAMC 12.22 A.33(c) and (e) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/25/2025
Issuing Office
Valley
Current Status
Issued on 3/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/6/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 PETER MOSESIAN
Corrections Issued 12/15/2024 PETER MOSESIAN
Quality Review Completed 12/19/2024 OMID HEDAYAT
Building Plans Picked Up 1/7/2025 APPLICANT
Applicant returned to address corrections 2/12/2025 DANIEL ABRAMYAN
Applicant returned to address corrections 3/18/2025 DANIEL ABRAMYAN
Plan Check Approved 3/20/2025 DANIEL ABRAMYAN
Issued 3/25/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/26/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 12/26/2024 HISASHI KOBAYAKAWA
Specific Plan Cleared 1/16/2025 JULISSA LOPEZ-HODOYAN
ZI Cleared 1/16/2025 JULISSA LOPEZ-HODOYAN
Roof/Waste drainage to street Cleared 1/25/2025 DARIN LAM
Grading Pre-Inspection Cleared 1/31/2025 CHARLES POWELL
Address approval Cleared 2/28/2025 LIAM ODONOVAN
GPI Written Notices Cleared 3/18/2025 PETER MOSESIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

PLUMBING-Final 7/24/2026    Time Frame: 1-3
ELECTRICAL-Final 7/24/2026    Time Frame: 1-3

Inspection Request History

PLUMBING-Rough 5/5/2025 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 5/14/2025 Corrections Issued ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 5/20/2025 Approved DANIEL VERA
Footing/Foundation/Slab 5/20/2025 Approved DANIEL VERA
Deputy Reinf. Concrete 5/27/2025 Conditional Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 6/20/2025 Partial Approval ASHLEY THOMPSON
Special/Order Compliance 8/20/2025 Corrections Issued ASHLEY THOMPSON
Deputy Wood Construction 9/26/2025 Conditional Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Partial Approval ASHLEY THOMPSON
PLUMBING-Rough 10/2/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 10/7/2025 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 10/31/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 10/31/2025 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 10/31/2025 Not Ready for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 11/14/2025 Corrections Issued ASHLEY THOMPSON
Green Building Rough 11/14/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 11/14/2025 Partial Approval ASHLEY THOMPSON
Shower Pan 11/14/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 12/2/2025 Approved ASHLEY THOMPSON
HVAC-Rough 12/2/2025 Approved ASHLEY THOMPSON
Insulation 12/5/2025 Approved EVAN COOPER
Drywall Nailing 12/18/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 12/30/2025 Approved ANDREW NAVE