13043 W ROSE AVE 90066

Certificate Information: 13043 W ROSE AVE 90066

Application / Permit
24014-20000-05365
Plan Check / Job No.
B24VN24881
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF EXISTING GARAGE AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). PORTION OF EXISTING GARAGE TO BE REMOVED AND ADD NEW CARPORT. WORK DONE PER ENGINEER DESIGN. **NFPA-13R FIRE SPRINKLERS TO BE INSTALLED THROUGHOUT**
Permit Issued
Issued on 3/6/2025
Issuing Office
Current Status
CofO Issued on 9/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2024 APPLICANT
Assigned to Plan Check Engineer 12/13/2024 ARTIN ZARUKIAN
Corrections Issued 12/14/2024 ARTIN ZARUKIAN
Building Plans Picked Up 12/19/2024 APPLICANT
Applicant returned to address corrections 2/19/2025 MADISON ODELL
Issued 3/6/2025 APPLICANT
CofO in Progress 9/2/2025 WILBER ROSALES
No Progress 9/2/2025 DAVID FEILER
CofO in Progress 9/2/2025 DAVID FEILER
Permit Finaled 9/5/2025 RICHARD STEINBACH
CofO Issued 9/5/2025 RICHARD STEINBACH
Permit Finaled 9/5/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 12/30/2024 ANTHONY MAINEZ
Specific Plan Cleared 12/30/2024 RICHARD WOO
Eng Process Fee Ord 176,300 Cleared 1/2/2025 ANTHONY MAINEZ
Sewer availability Cleared 1/2/2025 ANTHONY MAINEZ
Construction near power lines Cleared 1/10/2025 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 2/18/2025 AMBER CAMPBELL
GPI Written Notices Cleared 2/19/2025 MADISON O'DELL
Grading Pre-Inspection Cleared 2/19/2025 MADISON O'DELL

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/27/2025 Partial Approval MICHAEL ALLEN
Underground Mechanical 3/27/2025 Approved MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 4/1/2025 Partial Approval MICHAEL ALLEN
Piling/Pier/Caisson 4/1/2025 Approved MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 4/7/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 4/7/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Corrections Issued TEMISTOCLES CAAL
Structural Steel Frame 4/28/2025 Corrections Issued TEMISTOCLES CAAL
Deputy Wood Construction 4/29/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Approved MICHAEL ALLEN
Structural Steel Frame 5/1/2025 Corrections Issued MICHAEL ALLEN
Wood Frame 5/1/2025 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 5/9/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 5/9/2025 Approved JESUS PINEDA
Green Building Rough 5/9/2025 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 5/9/2025 Approved JESUS PINEDA
PLUMBING-Rough 5/9/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/19/2025 Approved MICHAEL ALLEN
Green Building Rough 5/19/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 5/19/2025 Partial Approval MICHAEL ALLEN
Structural Steel Frame 5/19/2025 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 5/19/2025 Approved MICHAEL ALLEN
Shower Pan 5/23/2025 Approved JESUS RODRIGUEZ
Underground Mechanical 5/28/2025 Approved MICHAEL ALLEN
Insulation 6/2/2025 Corrections Issued JAYLIN GRAVITTE
Insulation 6/4/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 6/6/2025 Approved MICHAEL ALLEN
Special/Order Compliance 6/6/2025 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 6/9/2025 Approved MICHAEL ALLEN
Special/Order Compliance 6/9/2025 Partial Inspection JAYLIN GRAVITTE
ELECTRICAL-Final 7/29/2025 Approved WILBER ROSALES
Final 7/29/2025 Corrections Issued WILBER ROSALES
Green Building Final 7/29/2025 Approved WILBER ROSALES
HVAC-Final 7/29/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 7/29/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 7/29/2025 Approved WILBER ROSALES
HVAC-Final 8/19/2025 Approved WILBER ROSALES
Final 8/21/2025 Not Ready for Inspection WILBER ROSALES
Final 8/29/2025 OK to Issue CofO WILBER ROSALES