1301 S FIGUEROA ST 90015
Certificate Information: 1301 S FIGUEROA ST 90015
- Application / Permit
- 24014-20000-05359
- Plan Check / Job No.
- B24VN24864
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (14) Community Center operated by governmental agency
- Work Description
- Eplan Renovation of the (e) West Hall of the Los Angeles Convention Center. Remove portion of (e) plaza & enclosure to accommodate the new construction of convention center expansion. Egress modification & construction of interim exterior envelope.
- Permit Issued
- Issued on 12/12/2025
- Issuing Office
- Metro
- Current Status
- Issued on 12/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2024 | GARO TELMI |
| Corrections Issued | 12/30/2024 | GARO TELMI |
| Quality Review Completed | 1/3/2025 | DANIEL CHAN |
| Plan Check Approved | 12/11/2025 | GARO TELMI |
| Issued | 12/12/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Stewart,, Heather D; Lic. No.: C39145 | POPULOUS 4800 MAIN ST #300 KANASAS CITY, MO 64112 |
| Contractor | Pcl Construction Services Inc; Lic. No.: 1055307-B | , |
| Engineer | Beaman,, Derek; Lic. No.: S4680 | 1301 5TH AVE 3200 SEATTLE, WA 98101 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Footing/Foundation/Slab | 7/14/2026 |
| Excavation/Setback/Form/Re-Bar | 7/16/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/18/2025 | Partial Approval | PAUL BAZERKANIAN |
| Deputy Shotcrete | 12/23/2025 | Conditional Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 12/23/2025 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 1/8/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 2/11/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 2/25/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 3/4/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 3/4/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/4/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 3/6/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 3/6/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/6/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 3/10/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 3/10/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/10/2026 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/12/2026 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 3/12/2026 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 3/17/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 3/17/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 3/18/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 3/18/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/18/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 3/19/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 3/19/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 3/19/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/19/2026 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/20/2026 | Not Ready for Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/21/2026 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 3/23/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 3/23/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 3/24/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 3/24/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 3/24/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 3/25/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 3/25/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 3/25/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/25/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 3/27/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 3/27/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 3/27/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/31/2026 | Not Ready for Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 4/1/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 4/2/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 4/2/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 4/2/2026 | Partial Approval | DAVID BURKHEAD |
| Special/Order Compliance | 4/2/2026 | Approved | RONALD JIMENEZ |
| Footing/Foundation/Slab | 4/3/2026 | Not Ready for Inspection | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 4/7/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 4/7/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 4/7/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 4/7/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 4/13/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 4/13/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 4/13/2026 | Approved | DAVID BURKHEAD |
| Footing/Foundation/Slab | 4/13/2026 | Partial Inspection | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 4/14/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 4/14/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 4/14/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 4/14/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 4/16/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 4/16/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 4/16/2026 | Not Ready for Inspection | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 4/17/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 4/17/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 4/17/2026 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 4/18/2026 | Partial Approval | MARTIN TAVITIAN |
| Deputy Reinf. Masonry | 4/28/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 5/1/2026 | Partial Approval | MARTIN TAVITIAN |
| Deputy Reinf. Concrete | 5/5/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 5/6/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 5/6/2026 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 5/14/2026 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 5/26/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 6/1/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 6/3/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 6/5/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 7/10/2026 | Partial Approval | RONALD JIMENEZ |