23444 W VICTORY BLVD 91367

Certificate Information: 23444 W VICTORY BLVD 91367

Application / Permit
24014-20000-05335
Plan Check / Job No.
B24VN24712
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Two story addition to single family dwelling and remodel of house.
Permit Issued
Issued on 1/3/2025
Issuing Office
Current Status
CofO Issued on 9/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 KHUONG TRUONG
Corrections Issued 12/17/2024 KHUONG TRUONG
Quality Review Completed 12/19/2024 PRANITA SHAH
Plan Check Approved 1/2/2025 KHUONG TRUONG
Issued 1/3/2025 APPLICANT
CofO in Progress 7/15/2025 GEVORK IPCHYAN
Permit Finaled 9/6/2025 MICHAEL PELHAM
Permit Finaled 9/6/2025 MICHAEL PELHAM
CofO Issued 9/6/2025 MICHAEL PELHAM

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/16/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/18/2024 CARLOS AGUILERA
Sewer availability Cleared 12/24/2024 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/19/2025 Conditional Approval GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 3/19/2025 Corrections Issued GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 3/21/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 3/24/2025 Approved GEVORK IPCHYAN
Drywall Nailing 4/4/2025 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Corrections Issued GEVORK IPCHYAN
Deputy Wood Construction 4/8/2025 Conditional Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Partial Approval GEVORK IPCHYAN
Insulation 5/5/2025 Not Ready for Inspection ROBERT GOLD
ELECTRICAL-Rough 5/12/2025 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 5/12/2025 Not Ready for Inspection GEVORK IPCHYAN
Deputy Wood Construction 5/19/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 5/21/2025 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 5/21/2025 Not Ready for Inspection GEVORK IPCHYAN
Rough-Elec/Plmb/HVAC 5/21/2025 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval GEVORK IPCHYAN
Interior/Exterior Lathing 5/29/2025 Partial Approval GEVORK IPCHYAN
Shower Pan 5/29/2025 Approved GEVORK IPCHYAN
Insulation 6/6/2025 Approved ROBERT GOLD
Interior/Exterior Lathing 6/6/2025 Approved ROBERT GOLD
Drywall Nailing 6/11/2025 Not Ready for Inspection GEVORK IPCHYAN
Drywall Nailing 6/16/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 7/9/2025 Not Ready for Inspection GEVORK IPCHYAN
Final 7/9/2025 Corrections Issued GEVORK IPCHYAN
Green Building Final 7/9/2025 Not Ready for Inspection GEVORK IPCHYAN
Green Building Rough 7/9/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Not Ready GEVORK IPCHYAN
Smoke Detectors 7/9/2025 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 7/14/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 7/14/2025 Approved GEVORK IPCHYAN
Final 7/14/2025 OK to Issue CofO GEVORK IPCHYAN
Green Building Final 7/14/2025 Approved GEVORK IPCHYAN
HVAC-Final 7/14/2025 Approved GEVORK IPCHYAN
PLUMBING-Final 7/14/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 7/14/2025 Approved GEVORK IPCHYAN