16933-16935 W BOSQUE DR 91436

Certificate Information: 16933-16935 W BOSQUE DR 91436

Application / Permit
24014-20000-05332
Plan Check / Job No.
B24VN24686
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL (ONLY 2'0" WALL TO REMAIN): REBUILD SINGLE FAMILY DWELLING TO MAKE A 75'10"X535'4" IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 13'10"X23'10" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e), 20'0"X20'0" 2-CAR GARAGE, 5'8"X10'9" FRONT TRELLIS, 10'0"X46'0" REAR TRELLIS, 10'6"X9'0" PORCH, AND A 7'0"X27'6" REAR PATIO. (NFPA 13 D FIRE SPRINKLERS REQUIRED THROUHGOUT) [1 OF 3]
Permit Issued
Issued on 4/25/2025
Issuing Office
Current Status
CofO in Progress on 6/10/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/4/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 MARVEL DELACRUZ
Corrections Issued 12/7/2024 MARVEL DELACRUZ
Quality Review Completed 12/11/2024 JASON HEALEY
Building Plans Picked Up 12/17/2024 APPLICANT
Applicant returned to address corrections 3/20/2025 MARVEL DELACRUZ
Applicant returned to address corrections 4/23/2025 MARVEL DELACRUZ
Plan Check Approved 4/25/2025 MARVEL DELACRUZ
Issued 4/25/2025 APPLICANT
CofO in Progress 6/10/2026 THOMAS FINNILA

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/23/2024 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/23/2024 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/23/2024 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/23/2024 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/23/2024 LEE GUILBEAUX
Permit Cleared 12/23/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/23/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/24/2024 LEE GUILBEAUX
Distance to fire station Cleared 2/27/2025 PATRICK PEREZ
Hydrant and Access approval Cleared 2/27/2025 PATRICK PEREZ
Address approval Cleared 4/5/2025 COLIN LOREDO
Trees in Parkway Cleared 4/16/2025 MIGUEL ORNELAS
Low Impact Development (LID) Cleared 4/18/2025 MITESH PATEL
GPI Written Notices Cleared 4/23/2025 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 4/23/2025 MARVEL DELACRUZ
Roof/Waste drainage to street Cleared 4/23/2025 RYAN CASTRO
Sewer availability Cleared 4/23/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Chrysostomo,, Anderson; Lic. No.: L9216 9592 ERSKINE DRIVE      HUNTINGTON BEACH, CA 92646
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/10/2025 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 6/12/2025 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 6/13/2025 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 6/17/2025 Conditional Approval ROBERT GOLD
Deputy Steel/Welding 6/20/2025 Conditional Approval ROBERT GOLD
Underground Mechanical 6/26/2025 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 7/2/2025 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Not Ready for Inspection THOMAS FINNILA
Deputy Steel/Welding 7/16/2025 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 7/17/2025 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Partial Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Corrections Issued THOMAS FINNILA
HVAC-Rough 9/17/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 9/17/2025 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 9/18/2025 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 9/29/2025 Approved THOMAS FINNILA
HVAC-Rough 9/29/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 9/29/2025 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Partial Approval THOMAS FINNILA
Wood Frame 10/3/2025 Partial Approval THOMAS FINNILA
HVAC-Rough 10/10/2025 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 10/16/2025 Conditional Approval THOMAS FINNILA
Green Building Rough 10/16/2025 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 10/16/2025 Approved THOMAS FINNILA
BUILDING-Rough-Frame 10/22/2025 Approved THOMAS FINNILA
Interior/Exterior Lathing 10/22/2025 Not Ready for Inspection THOMAS FINNILA
Shower Pan 10/22/2025 Not Ready for Inspection THOMAS FINNILA
Insulation 10/27/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/27/2025 Partial Approval MORRIS JACKSON
Shower Pan 10/27/2025 Approved MORRIS JACKSON
Drywall Nailing 11/3/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/10/2025 Approved THOMAS FINNILA
PLUMBING-Final 5/6/2026 Approved THOMAS FINNILA
ELECTRICAL-Final 5/11/2026 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 5/12/2026 Approved THOMAS FINNILA
ELECTRICAL-Final 5/18/2026 Approved THOMAS FINNILA
Final 6/9/2026 OK to Issue CofO THOMAS FINNILA
Footing/Foundation/Slab 6/9/2026 Approved THOMAS FINNILA
Green Building Final 6/9/2026 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/9/2026 SGSOV Approved THOMAS FINNILA
Service/Power Release 6/9/2026 Approved THOMAS FINNILA
Smoke Detectors 6/9/2026 Approved THOMAS FINNILA